Thumbnail for SORTING SOME VERY DODGY WORK OUT

SORTING SOME VERY DODGY WORK OUT

Watch on YouTube

Video summary

The video documents a challenging renovation project focused on replacing dodgy window lintels and addressing structural issues within a stairwell area. The work begins with the removal of existing glass and frames to prepare for the installation of new concrete lintels, a task that requires careful scaffolding setup due to the difficult geometry of the stairwells. The team utilizes thermalite blocks, which can be easily chopped with a saw, to create custom openings and fill gaps without disturbing the surrounding brickwork. This method proves particularly useful when dealing with large, pre-existing concrete lintels that span across both walls of a cavity, as removing them entirely would be too risky; instead, the team builds up around them while managing potential cold bridges in the middle of the landing. A significant portion of the process involves intricate masonry work to ensure the new structure is level and secure before the final window installation. The builders use screw ties and tie wires to connect the new blockwork to the existing frame, effectively sealing gaps and providing temporary support until the new windows are fitted. They encounter some complications with the positioning of certain components, such as temporary packers that indicate flexing in the structure, which they address by adding silicone seals. Despite these hurdles, including a particularly treacherous 1500 concrete lintel on a stairwell, the team manages to integrate the new blocks seamlessly, bonding them into place to restore strength and stability to the area. The project concludes with the successful integration of the new blockwork and cavity trays, allowing the team to focus on tidying up and finishing the exterior courses. Although some original elements like the large concrete lintel must remain in place due to safety concerns regarding height and structural integrity, the modifications ensure the building is weather-tight and structurally sound. The builders express relief that the difficult section is complete, noting that while there will be minor imperfections like cold bridges, they are located in areas where they will not significantly impact the overall performance of the house. With the main structural repairs finished, the focus shifts to final detailing and preparing for the next phase of the renovation.
Read the full video transcript
Happy Independence Day if you're watching in America. >> Well, if you asked me this morning, I wouldn't have said that would have gone in that easy. Happy Independence Day if you're watching in America, 4th of July. I mean, it's not You'll be in bed at the moment cuz it's uh just after 8:00 a.m. in England, 5 hours ahead. So, that's what we got up to. Just [bell] see the uh timbers cut off up there. It's all ready to come out. It's all prepped, ready for lintils. So, we need to get inside. As you can see, Alex put the ladder up there. Get get some kind of contraption set up to stand on. Get the glass out first. There he is. Um, glass out. Cut the frame out, lintle in, and then we can build everything up then. It's a block work on the inside obviously up to the existing lint which will be there. And that's finished then on the inside. And then the outside will carry on all the way up to the top eventually. We're going to get probably another two courses up above the window today. That's the plan. So, we'll take you inside and see what's going on. Hey, hey, [music] hey. Number n. There you go. You're going to have seen us making right share that on the time lapse. Oh, it's a lot cooler now. That's the bit I was worried about. So, [snorts] not the best, but decorates them now. Um stairwells are very hard to scaffold and work on. So this isn't too bad for us. It works out just right. Planks off the top off the top floor across onto the window sill and then a ladder for a little cl across. There's not going to be a lot of work going on on this. This is mainly just for fettling and getting the glass out and stuff. Uh taking the pockets out for the lintils and inserting the lintil which is going to be a 1500 concrete. So, next job is rattler mate for the uh got two grabbers. So, whack these out. Probably uh yeah, there's no there is no silicon. They just trimmed it. So, whack these out. Frame out. Cut the frame out just there. Well, in line with the brick work with that. Jobs are good. And as you can see, we're all ready to go outside. >> [snorts] >> Nice and cool today. Nice breeze. Judging by the trees here, it's always breezy cuz all the trees are growing lean to the left. So, yeah, it's enough waffle. Let's get you set up. Push the back in. They're ready to cut into the pockets. Not butching them. Got me blade, haven't we? >> Yeah. >> I'll get out that we can hit back in again. Okay, now Next Natasha. >> [music] >> N hey. Hey. Hey. Hey, hey, hey. Heat. Heat. [music] Heat. Heat. N. [music] >> [music] [music] >> Heat. Heat. Heat. Heat. Heat. Heat. [music] Heat. [music] >> [music] >> Occasionally I will endorse thermalites because you can just chop them up with a saw. Makes our job a lot easier. So have to break mix on lintil in. Might even get this built up from this side. Just work that work that way. Work together cavity opened up cuz it's now wall. Just a bit to take off the top. That's that's a proper big concrete lint that goes across there. So we're just going to build up the front of that. I'm not going to try and take it out and move it cuz it it covers both both skins. Another weird invention. And I'll just chop out the mortar out of there. I don't want to disturb the brick work. Just leave it so there's a a gap basically. Stop the cold bridge. Right. Go and get a bucket. Right. Great time over. Got that bruise in. We we cut that down on Thursday when we realized. So that's ready to go in now. It's been measured. It's been checked. Uh we have got a hold. I need to patch this at the back here. We got something to sit on. He's uh patching up. So we've got a full seating. We'll find that end. I'll just go and get a small mix on. I don't need a massive mix for this. I think I might get the uh the drill just to drill those the cavity out there and get this hoovered out so it's ready to bed on. And then it's um angle line on the on the outside with the cavity tray in it. So, um, yeah, I think we'll, um, I think we'll do the block work and we'll stick the cavity tray rather than try and build it in. All our gauge is going to be out. Yeah. To get the to get the cage straight to go past the L. We have to take another load of block work out to get above it. So, and that's solid concrete. This uh Yeah, we'll sort something out. Can't get prepped. Yeah. [music] Hey. Hey. Hey, hey, hey. [music] Heat. [music] Heat. >> [music] >> Well, if >> you asked me this morning, I wouldn't have said that would have gone in that easy. >> This morning, Alex, I just want to go back to bed. I felt really bad after yesterday. We had a 12 hour a 12-hour day of stay on on an easy looking steel as I thought we were going to have an early dart on that. We got home at 8:00. But anyway, back to today. We're both really dreading this bit, but um that was a dream, wasn't it? >> Well, look at it. It's a 1500 concrete lentil on a stway. It's about as like treacherous as you could make it. The thing that made it all different for us here was um thermalite blocks. Just being able to chop it chop the thing out. That made a massive difference. >> If you seen if you seen there, it's back to fiber lights there. >> They're not fiber lights. They're 7 Newton concrete then. >> Oh, are they concrete? >> Yeah. And above. So, this is a really good idea this because it's um giving all this strength back. There's the lintil which stretches across the cavity onto the outside. That's the only thing that's stopping it falling, I think. And then you've got well just hacked out there and just thrown the fiberite blocks, thermalite blocks and then those put in which are leaves. But all this is irrelevant now cuz all this is getting blocked up. Got our pieces cut for across here and then tray on top of that and yeah cooking on gas. Amazing. So we just get ourselves organized now and work between the two sides together. >> After these pieces go in, you're going to need your ladders, aren't you? throughout there. >> Yeah, cuz we can't really continue till the train is in, which >> we need we need someone on both sides now. You can you can spread and butter the blocks now. You can put them in and plumb and everything. >> I'll um I'll get the set up for you. >> Yeah. Yeah. So, I'm going to get these there's the cuts there to go across here to bring us back into course with the block work. And as I said, we've got our screw ties to go in and we've got one tie wire. One tie wire. So, one tie wire is going to get us here. And then we'll probably just use two of the screw ties and build them in just straight in. Like I know it's not supposed to be used like that, but we'll put the plug on and just build them in like that. We need two instead of go buy a whole pack of tie wires for one tie wire. No point. No one got a garage full of them. So, we'll we'll make do for today, right? Uh, let's put you somewhere on time lapse. Put it out there when Alex gets up there and we'll get this lot in >> [music] >> Hello. I'm outside now. Alex just got that course across for me, which you would have seen on time lapse. Now, um need a screw tie in that end. Tie all that into that corner. See a wall coming off there. And then um we could do with getting this front in now and getting the cavity training built in. Have to just rig that bit out there. Yeah. Come and back roller damp. 20 t wires. 30 quid. Which one >> all together? Oh, >> it's 9 quid. The 20 towers is 9 quid and 450 damp. So, um, what's happening now? You putting that screw tie in. >> Screw ties in, isn't it? >> No. Where? >> Supposed to put it on top. Stick another one in cuz there's not much to tie into underneath there. Okay. >> Yeah, another screw tie in there. And then we can get this [laughter] we'll get this front then. Just get this scaffold organized a bit first. [music] helps remove the camera. There you go. Instead of breaking this in with bricks, put the half in and block bond it. So the blocks actually bonded in this first section. Nice straight proper nice strong job. And then we've got this to go under here drilled screw to the frame. So it's going to act as a seal till the new window is put in. And it's going to be a prop for the lintil as well. There you go. You got the battery. >> Have I got it? >> Yeah. See, I need them. Can you reach over this? Where do we hold it in place? Just push down and do it. Everything's wrong, is it? Um, we have chopped up the window, haven't we? It's definitely is getting changed. >> Yeah. Show friends are a bit fat. The water's a bit dry. Okay. supposed to be at the bottom of an it should be sat on, shouldn't it? >> E. >> Yeah, that means it's flexing, isn't it? That's temporary packer in there. I have to put a bit a bit of silk across that as well. Yeah, it's temporary. [cough and clears throat] >> [music] >> Star up. [music] It won't stop. [music] It was [music] 11. Heat. Heat. [music] >> [music] [music] >> Hey. [music] [music] Hey. Hey. >> [music] >> You want [music] you star you. [music] You are you. >> [music] >> You know, you know, [music] >> [music] [music] >> Hey, [music] hey, hey. [music] >> [music] [music] >> Hey, [music] hey, hey. >> [music] [music] >> Hey, hey, hey. [music] >> [music] [music] >> Ah, [music] ah. >> [music] [music] >> a >> [music] [music] >> Ah, [music] heat. Heat. Heat. [music] >> [music] >> Heat. Heat. [music] >> [music] >> Heat. Heat. [music] Heat. Heat. [music] Heat. Heat. Did you raise your one? I have to edit that out. There you go. Tied in. Screw tie in. Another full course. Then another cut across the top. I'd love to take this out, but look at the state of it. We're not really at a good height for propping things. It's already dodgy on the back. So, this is staying in. It's going to be unfortunate cold bridge, but it's going to be in the middle of the landing. So, it's not going to make any difference to the house. So, yeah, get that in after after dinner. Once that's in all pointed up, I can concentrate on this side. And now I can concentrate on tidying that lot up. >> [music] [music]