Video summary
The Moretown Selectboard convened on September 8, 2026, to address critical delays in the Town Hall renovation project and urgent infrastructure needs across the town. Library Director Cody Stevenson highlighted significant frustration regarding the stalled renovation, which has been hampered by a lack of collaboration with the Finance Review Committee despite nearly a decade of community engagement and volunteer efforts. The board recognized the imperative to resolve deferred maintenance, accessibility, and life safety issues before costs escalate further, leading to a decision to direct the Finance Committee to immediately meet with the Town Hall Committee and the Vermont Bond Bank. This action aims to determine total project costs and financing options for an early 2027 bond vote, with a target decision expected by late October or early November.
Infrastructure updates dominated the agenda, covering repairs along Lover's Lane, River Road, Mountain Road, and safety enhancements on Jones Brook. Due to environmental concerns about placing rock in the Winooski River, FEMA is reviewing a repair plan for Lover's Lane that utilizes soil nails instead of stone fill, reducing the budget from an initial $2.5 million to approximately $1.6 million for repairs and $900,000 for the soil nail installation; construction is anticipated between March and October 2027 with a temporary bridge required by December. On River Road, the board voted to accept a higher bid of $418,770 from Kingsbury Construction over lower bidders due to concerns regarding quality and reliability, while Mountain Road was scheduled for closure on September 9 with hopes of reopening by the weekend. Additionally, the board discussed installing guardrails along a 440-foot section below Sarah's house on Jones Brook using available FEMA funding to address safety hazards from steep drops and slippery winter conditions.
The meeting also covered various administrative decisions, financial adjustments, and community projects ranging from vehicle procurement to facility upgrades. The board decided to trade in the current non-running Town Hall truck for a 2026 model to avoid emissions risks associated with newer vehicles, while acknowledging existing town debt and interest rates in their financial planning. Financial projections extending to 2031 were reviewed alongside potential repairs needed by 2032, leading to an approval of a quarterly volunteer recognition program starting with Caleb Dean and Rodney, funded through local businesses rather than certificates. The board approved increasing the Health Officer's annual reimbursement from $300 to $600 due to increased workload, authorized replacing the History Center roof with shingles for a 50-year guarantee, and contracted for a mobile dehumidifier unit to address moisture in the town garage.
Finally, the Selectboard addressed property acquisitions for green space and other community initiatives, noting that the demolition of Schaefer's House is scheduled for December as owners move to Pennsylvania, while participation from three Douglas properties remains undecided until year-end. Discussions emphasized a preference for minimal intervention maintenance on acquired lands, such as allowing natural growth or planting trees sourced from Burlington, rather than active mowing, though safety concerns regarding unhoused individuals at a specific state-owned park corner influenced the decision-making process. The board also planned a presentation on local lot taxes by an expert from Weightsfield, scheduled a meeting with Kathleen Ramsay regarding Middlesex's lot tax process, and approved the Friends of the Mad River's native seed collection. After removing resolved items like Pony Farm parking issues and land use policy updates from pending business, the meeting concluded with administrative updates and a move into executive session for confidential employee discussions upon request.
Read the full video transcript
All right, we're everyone all set here.
>> All right, welcome everyone. It is the
Moretown Select Board. It is Tuesday,
>> recording in progress,
>> September 8th. Uh we're here at 79
School Street at the John Hog meeting.
Salute to John as we always do, right?
Um so we're going to go ahead and start
with public comment. Let's just see we
have a lot of people out here. A raise
of hands. How many people can public
comment today?
>> All these. All right, you can take it.
>> All right. Well, I had to write it down
so I wouldn't forget.
everything I wanted to say.
>> Nothing. I don't know if you if you
could announce your presence.
>> I'm Stevenson. I'm the library director.
I'm kind of here in my capacity as a
town hall committee member. So, the
first thing I just want to do is
recognize the service of everyone in
this room. So many of you are volunteers
basically and you're doing your best to
make this town run. So, I really
appreciate that. And I also want to say
that as an employee these past 10 years,
I have done my best work, my best to
work within the town's existing systems
and processes, both as library director
and committee member. However, I'm
finding I can no longer do that in good
conscience with conscience with the
current process for the town hall
project. Since 2017, when the select
board first invited the library to move
into the town hall, I've been involved
in some way in the project. There is now
nearly 10 years of information on hand
from robust community engagement and
input on what the building should be
used for to a complete set of
construction documents outlining a basic
renovation project to keep the building
standing and functional for all
residents. We have made at least six
formal presentations to the board and
community about the project, countless
other meetings like this, and have
included information report nearly every
year. This past spring, when it became
clear that a funding plan was needed for
the now shovel ready project, the
finance committee was asked to weigh in.
Without prior involvement by the members
or understanding of the work done to
date on the project beyond one meeting
that we had together, the recommendation
at the June 15th select board meeting
was made to refrain from a bond vote
until FEMA questions were answered.
As a Morttown resident and a taxpayer, I
definitely understand this difficult
situation that the town is in and the
lingering uncertainty and rising costs
and the pressure that really puts on
everything. I get it. I pay taxes here,
too.
It also seems somewhat shortsighted to
me to delay as we can no longer ignore
the needs of the building and the price
tag for fixing it also continues to
escalate. At that June meeting, my
understanding from the discussion was
that the finance committee and the town
hall committee would work together to
explore and gather information on
funding packages so that we could be
ready for a bond vote in early 2027.
So far, despite repeated requests, the
finance committee has refused to meet
until they are directed to do so by the
select board. And so here we are now in
September, still without a clear
understanding of next steps and a very
real possibility of missing the
necessary timeline to get that vote out.
It is very frustrating and disheartening
to me to think that all of the hard work
done by over 20 volunteers, past and
present, on the town hall committee. All
the money we've spent to date will be in
vain due to this apparent lack of
commitment and collaboration.
I believe it is time for the select
board to get more involved in officially
supporting and moving this project
forward. The town hall committee has
more than done the work requested. Since
2021, we have reached out to the
community, determined the needs of the
building and found a path to address
them with a bare bones project that
takes care of all of the deferred
maintenance and accessibility and life
safety issues. In my view, the next step
is for you to raise awareness, share
your and provide information on the
project for the community. Then present
a bond vote which allows informed
residents to weigh in and make a choice
about the building. It is my hope that
the importance of having a space to
gather in and build community will be
recognized and that without and that
without that space we become not much
more than a collection of roads and have
to drive other places to find that
community connection. Either way, I
think it is time to let the community
decide.
While I'm no longer going to serve in my
capacity as town hall committee member,
I'm hopeful there will be new community
members that who will join that will
feel passionate about the building and
help you move the project forward. I'm
happy to be a resource for anyone and
will certainly share my perspective with
friends and neighbors on the importance
of preserving this community asset that
has been at the heart of Morttown for
nearly 200 years.
So, thank you for your time.
Thank you, Cody. Um, and thank you for
the time you put in both um as an
employee at the library and your time on
the committee.
And I'm sorry that you're frustrated.
>> Thanks. Appreciate it.
Well, I just to one thing that's a
little frustrating is that we've tried
to get a meeting with the finance
committee and it even brought it up at
our 818
select board meeting that saying we were
trying to and then it was after that
that I still asking if we could have a
meeting and I was informed by Cheryl
Lynn that the select board had to direct
the f more town finance committee to
meet
And I went, "Well, okay, but we we
discussed it on the 18th and then
unfortunately it's not." And then she
said, "Well, it has to be in the
meeting." I said, "Unfortunately, it's
not in the 818 meeting."
Um, and so now it's just a whole bunch
of other weeks have gone by, you know,
without having this meeting. And um one
of the things that we did as a town hall
committee was we met with uh some folks
in Warren
and just to see how did we go about
bonding you know a $10 million bond for
the for a new garage and you know they
gave us some very informative stuff I
won't
one of them was that meeting with the uh
Vermont the general in the city was
meeting with the um Vermont bond bank
was really a good first step to do and
we got to do that with the finance
committee I would assume. So if we can
come out of this meeting with at least a
direction that we can re you know meet
with the finance committee to start to
work on how we could do this I think
that would be a good you know which is
what we said back in June
>> and I'm not aware of any other
committees that can't meet unless
they're directed by to meet so it's just
it's just it's a
to work together and then we aren't
really getting to work together.
>> Can I clarify something?
>> Finance review committee is a committee
that was put together to make
recommendations to this board on
finances.
Linda Hazard volunteered to give her
time not as a finance review committee
person
but to work with you guys as grants.
Finance review committee
doesn't work on grants or anything like
that.
>> No, we don't there's no grant or right
now. We have one we're waiting to hear
about.
>> The town hall committee was formed to
make recommendations to the select board
on the town hall. It's the same idea.
>> I mean, it was great. Yes, Love Linder
has helped us going forward, but the
point was just to see what we could
figure out with the finance committee
and, you know, knowing what they know
about town finances and what it would
take and again meeting with the Vermont
Bond Bank and stuff like that just to
see what it would be, you know.
>> So, why don't we um I'm not trying to
push you off Cory, but we have the
agenda. We have a little business coming
up which should be within a half an hour
here.
>> That's great. I have to go to the
trustees meeting and I have so
>> resigned. So hopefully somebody out
there listening or here tonight is
excited to uh you know cheerlead this
project through. I just after almost 10
years I think to be done for a while.
>> I understand.
>> Yeah.
>> I can appreciate what you've done your
stuff.
>> Thanks.
>> Thanks Cory. Chris did you have anything
Chris? I have Can I get one and a half
pounds of the big stuff
>> and then a half pound of
>> the garlic? Yeah, no problem.
>> All right. After I went home on Sunday
and checked
>> Oh, for real?
>> I did.
>> All right.
Now, great. Unique garlic. This guy is
the best seed going. But anyways, all
right. So, um any is there any other um
uh public comments? I guess just
connected to what Fory was saying, the
we're doing a lot of work on how to
communicate the project to the public
and to the Morttown community and having
that bond piece in place. It affects our
messaging. It affects how we position it
to the community. And so we really do
have movement on on that piece of the
puzzle. And not only that, with our
capital campaign as well, you know, we
will we have fundraised, which you know
is how we did the last phase of the
construction documents and the
construction manager. But um and we will
continue to do that, but we're, you
know, we're kind of waiting to hear
about the $400,000 grant and, you know,
just trying to like at least get the
conversation going what it what it could
look like or what we could do with move
on, you know.
>> Um, so
>> I know we're waiting. We're going to
hear FEMA updates in the next thing
here.
>> Yeah. So,
>> is there anyone uh public comment there?
>> All right. So, let's go ahead and move
in. Thank you again, Corey. Thank you.
>> And uh Ray, why don't you
>> Chris,
>> did you want any more test updates? I'm
sure like we will meet again more test.
Everything's on track for Saturday.
Yeah, maybe just
>> we need a couple of volunteers to help
with parking
>> parking volunteers.
>> So, we've got over 25 volunteers for day
of and
>> 25 vendors. So, it's pretty full.
>> 25 how many vendors?
>> 25.
>> No kidding.
>> Yeah. What type of vendors do you have?
>> Um I wish I have this with me. Um so
>> it doesn't have to be like food.
>> Yeah. So, um like living tree lines will
be there.
Cider Press, um, Highlanders Lacrosse,
um, Little League, PTO, Friends of Eco,
>> historical society, the Planning
Commission, the stream table. I mean,
>> we'll have a more table.
>> We have a Waterberry River
>> stream table.
>> Stream table to find their
revitalization project.
>> Our bake off.
>> What is there a theme for the bake off
this year? story book eats. So, it's
based on, you know, it's like um Harry
Potter's favorite dessert, like from a
book. So, it might be like a book themed
dessert.
>> Very cool.
>> So, it'll be a full a full ring of
vendors.
>> That's good.
>> Well, good. Thank you for for all the
time you're putting in and doing.
>> Sometime we came in under budget on the
fireworks when every other town seemed
to get priced out of fireworks. We went
under by $1,500.
>> So, right.
>> I think we're coming well under budget
this year as well. So,
>> good. I know the music.
>> And there is a budget. So, even better.
All right. Well, thank you very much. If
there's nothing else, then we'll move on
on the agenda. Um Ray with FEMA stuff.
You guys all set? And we have Callie's
online by the way. Um or get the number.
So,
>> okay. So, um, guess I'll start off
talking about, um, Lover's Lane.
The last time we were here in early May,
um, when we decided whether we're going
to go with a bridge or fix the road,
um, and we decided that night to go
ahead with fixing the road. Um, FEMA
came back and wanted to review putting
the using a stone fill uh, repair job
rather than the um, soil nail thing. And
this review now has gone on for 3
months. But this weekend,
uh, I think we're close to an agreement.
They sent the final documents, I hope,
over today. Um, so it looks like we're
going to have roughly uh $2.5 million to
fix the road uh and that would include
the soil nail uh uh design.
U so and um
whatever the project comes out to be
dollar-wise,
it will be paid. Whatever goes over
under it's like an exact amount.
whatever we can verify
is what will get paid. So, um a major
part of that or is is the detour. What
do we do while the roads being uh
repaired? Uh and there's uh money for a
temporary bridge. We try to get one from
the state. Uh the state says
they didn't they don't have one. So, we
put out a bid uh for a temporary bridge
um based on having it put in by the 1st
of December and taken out, you know, uh
the construction period right now is
something like March to October.
But um
my concern and I looked at the road, the
temporary road that we have now with
with Martin and Caleb Dean who happened
to be over there at the same time. Uh I
wanted to look at it with Martin, make
sure that we we need to fix that road up
on the premises that we may not have a
bridge until March.
So um and so they're they're working on
that. Um, but I'm I'm very hopeful that
we'll have a bridge up before then, that
we don't have to take our chances with
the existing uh detour or fix that was
done. Um, the fix that was done has been
held up remarkably well. It was just a
quick fix and it's been, you know, as
you know, three years.
>> Yeah.
>> So, um, that's the lever's lane part of
things. Is there any questions about the
lever lane? I still don't understand
where the where the funding is coming
from for the for the temporary bridge.
>> It's it's it's going to be part of the
the FEMA it's part of the FEMA
obligation obligated project. It's part
of the 2.5 million. All right. We have
uh
I'm guessing there's $150,000 in there
for the temporary bridge. And did they
drop the other two million that was
supposed to be for
>> They did. They did. At this point, they
they lowered what the numbers they were
talking back about in May have come down
by over a million dollars. Um, but we've
been going back and forth. Uh,
the the Vermont emergency management
people have been really good. It's the
FEMA people have a hard time
understanding that we just cannot put
6,000 yards of rock in the Wii River.
It's there's no way we're going to get a
permit for that. And that's the kind of
the big hangup or what has been the big
hangup. And
but that's not where that's not where
we're at.
Uh we've got uh we have a design
engineer which uh I'm going to suggest
this little clipboard tonight that we go
forward with and that would be Auto
Creek Engineering
um to get a get a final design in
um
>> and I'm sorry is there less money
because the estimate for the repairs
were reduced or are they just giving us
less money and the town has to come up
with the remainder?
the
number. Okay. So they have two um
portions to repair the to pair the road
back to the existing condition and the
mitigation number. Yeah.
>> Okay.
So when we were using the number in May,
we were saying at that time we cannot re
we cannot repair the road back to the
existing condition because we can't get
a permit for that. Yeah.
>> And so the repair
should have been 2 and a half million
should have included the nail the soil
nails at that point. And then the
mitigation was on would be on top of
that. Okay. So they still are not
convinced of that although they're it's
not over yet. Uh they reduced that down
to one six 1.6 million roughly to repair
the road back to the existing condition.
still thinking about putting the stone
nail. Okay.
>> Okay.
>> And roughly 900,000 for the soil nail.
So, we're at 2.5 million, which
I believe based on their estimates will
work for the project. Um, we were hoping
to have more money to obviously do more
work. Um the big item is not the not the
slope going down the river. It's the
upside slope, right?
>> Yeah.
>> The go slope going down the river. It's
pretty visible. Uh and not, you know,
the damage is pretty visible. The upside
slope is not as visible, but it's there,
right? So,
>> and just one more question. The permit
for the river, is that a state or a
federal permit for putting that?
>> That' be a state.
>> That's a state. Okay. Although I guess
it they're not really sure if we uh if
the uh core of engineers would get
involved with that many yards of rock.
>> Okay.
>> But basically when we approached the
state about what the FE will want to do,
they said there's no way that they're
going to allow 6,000 yards of stone be
put in the river and push the river down
to water earth.
>> Y
>> which um
that's their Nice.
>> And then you think the construction will
be March to October of 27?
>> Yeah.
>> So, okay.
>> Aside from the cutting of the trees.
>> Yep.
>> Because of the bats, the trees, whatever
clearing we have to do has to happen
between, I believe, November 1st and
April 1st.
>> Yep. So, we're hoping to have a plan
together and get that done so the
project's not delayed.
>> It's just a federal requirement. Anytime
there's federal funding involved, you
have to you have to if you're removing
trees, even if you're not near a known
hibernacula or anything, it's got to be
in that window because then the bats
would be dormant and somewhere else. So,
yeah.
>> Yeah.
>> Thank you.
>> Um, this might be a simple question. Um,
but like where the slope field is like
right under the power line basically,
right?
>> Okay. and all that's going to get
nailed, but like is there something the
power company could do to like let the
vegetation grow up but not be impeded? I
mean, I understand it's probably like
highly erodable soils, but like it's got
to be connected to the or I don't know.
When I rode my bike through there last
time, I was like, this has to be
connected to the fact that there's no
vegetation right here.
>> I I think that's a valid question. Yeah.
I have not approached them.
>> Yeah. Like I just wonder if you know
they've got their own regulations and
but you know I just low growth stuff.
>> Yeah. I just wonder if they could do
something there or if maybe that
wouldn't even help. I don't know.
>> Yeah. I mean you know
>> most of the slope failure as you can
tell is right in that way.
>> Right.
>> Where there's no trees.
>> Yeah.
>> So that's slugs lane.
>> That's lane. Um
so uh this past last week we had uh the
bids out for River Road. Uh we had
several bids and um
we're our engineer Pat Ross Engineering
is recommending we go with Kingsbury.
Um I don't know Tom if you have this as
part of your paperwork there but if you
decide to go forward with that if you
could sign that decide to go to
Kingsbury.
>> Yeah. and it all feels included with
that. But um so the plan on River Road
would be uh if we if you decide to work
to Kingsbury, which we hope we do, um
they would probably shut down River Road
for about a week in early October to get
that cover in.
There's no there's no way to build a
detour there.
Um, so, um,
the town has purchased the culvert
separately on that one because because
of the schedule. It's a 12t diameter
cover that we wanted to make sure we
had. And
>> I think um, did everyone get the
recommendations?
>> Um, any questions on the recommendations
at all?
>> All right. So if there's no question for
>> because we weren't going with the low
bidder, we're going or the highest score
was the recommended one, right?
>> Yes.
>> Yeah.
>> Yeah. There were So the bits ranged um
from
the slowest
looks like 410,000
all the way up to 723,000.
And um based I actually I think there
was one more one that was lower than
that. There
>> waters waters
>> waters at 410. No
>> waters was 372 originally
and then was 410
>> right. Um but based on the the scoring
um and that's why I wanted those those
uh recommendations sent out to you guys
so you had an opportunity to take a look
through it. um because it was not the uh
the lowest bid. Um but if you have some
questions actually certainly ask Ray,
but the reasoning behind uh is really
based on quality of work. Uh and we've
had experience with the two other lower
biders and it just hasn't worked out. So
that certainly factored in to Kingsbury
Construction. They're right down the
road um as well. So that's good. Um, so
I'd make a motion to accept uh the
Kingsbury construction bid of $418,770
um for the project.
>> Second.
>> And that's uh River Road Culbert um
2.04.
Thank you, Cali. Any other discussion on
that? All in favor I. I.
>> Thank you. Thank you. Thank you. And
Anything
else right now? Uh,
Mountain Road, I put the list out. Uh,
we're on schedule to close the road
tomorrow,
roughly around 9:00. Um, and have it
open uh in a week's period. Uh we're
quite hopeful that if we don't hit any
ledge when we're digging that the culver
the road may be open by the weekend but
you know we're we're being conservative
in our posting that it may take a week
if we run into ledge.
But uh it's not that deep a culvert. Um
so we're really hopeful and there's a
culvert already there that we're
replacing. So we're we're only going
another 2T deeper than the culvert
that's there. So, we're hopeful that uh
it goes in fast and
gets it back open.
>> I believe that
>> we we did put the message boards up.
They've been up now for almost two
weeks.
>> So, um
people should know
>> communication's been out there. I've
seen it myself. So now what was the
comment I saw
posting or an email or something with
the
is the kids are going to walk
>> if if uh so if during the day if if if
the bicyclists are if kids need or not
necessarily the bicyclist but if if kids
need to go from one side of the comfort
to the other we we can we can make
arrangements to somehow make that
happen. But we're basically saying, you
know, no bicyclists, no cars.
>> But if you know, the kids have to go
across to get a car to go down to the
school, well then, you know, do
something.
>> So,
and the contractor is aware of that. So,
I think I think we're think we're in
good shape for that.
Um,
okay. The other question. Okay. We
talked about um Lovers Lane. I don't
have a contract for Otter Creek
Engineering, but uh it it came down to
Otter Creek and um uh
Stantech and um
we decided that Otter Creek was the best
one for this project. Um,
I'm still working on some of the words
of the contract to get that done, but uh
I don't know if you what I'd like to say
is um if we could make a motion to have
one of the select boards sign the
contract when I get it done rather than
wait for the next meeting. Is that
possible or would you guys rather see
the contract before you make that
motion?
>> I think we should probably see the
contract, but
I I think we can
I'm comfortable with you talking with
Audit Creek and letting them know this
is a situation. We just need to make
sure before we sign anything that it's,
you know, all those eyes and te's are
dotted and crossed that it's to your um
>> Okay.
>> 100% specs. There's no,
>> you know,
>> Okay.
>> Because I hate to, you know, because
we're on the line for it and I I just
want to make sure everything is done
that way. Not that we don't trust
anybody. Yeah. Yeah. Uh, no problem.
>> I just So, the the last the last item
and I nearly need I wanted to talk on
that unless we want to, you know, it's
not that difficult for three of us to I
mean,
>> yeah. You know what? If if something
we'll talk, Ray and if it's really
critical, then I can call a special
meeting and three for us can do
something online or something
>> and just redo it with you and sign off
on. Okay.
>> What project is this for?
>> That's the uh Lovers Lane project.
>> So, the last item is a question of guard
rail on Jones Brook. Uh and um Callie's
probably familiar with it. U
when we fixed uh Jones Brook Road, we
well, let me back up. When the flood
went through along Jonesburg Road, there
was about a 700 foot section
of road that washed out and it took out
there was no guardrail there before, but
there was trees along the road to, you
know, so people wouldn't go off the road
into the brook. So now we have this
section of road um right next to the
brook. There's no trees and we raised
the road up about 2 feet. So, it's it's
been that way since we've done the
rebuild for two years, but I've had a
lot of complaints about it. And I don't
know if Callie's heard anything or not
or how you feel about that, Cali, but uh
uh
>> where is it?
>> Right below my house on the right side,
you know, from my house down to the
first culvert on the right.
>> Oh, by Sarah. Yes.
>> Down by Sarah. Yes. Um, so it looks like
we would have enough money to do the
guardrail. The guardrail is roughly
$8,000 plus traffic control. So figure
$10,000.
Um, and I'm sorry, it's $440 ft. It's
not 700 ft. So it's 440 ft of guard rail
we're putting in. It wasn't there before
the flood, but I'm pretty sure FEMA will
pay for this considering what the flood
did. And
uh we've been putting off the guard
railroad because it's a son of a gun in
the p for snow plowing with a guard
railroad area. But I've talked to Martin
about it. I told him we've had I have
had a lot of complaints
>> about people being afraid they're going
to slide off the road.
>> Yeah. Yeah. It's a pretty good drop off
>> with the icy road or something or snow.
>> So
I don't know. Cali, do you have any
thoughts about that at all?
I'm surprised that there's guardrails at
the culvert above our house and not
guard rails and that spot below your
house and at the culvert that's just
below my house because
>> the spot down below your house is
slippery in the winter coming down that
hill and if you go off you're going off
>> okay
>> into the brook and they definitely did a
lot of work around the culvert just
below my house where now steep that if
you're going to come down that hill and
go off, you're going to go down in and
I'm surprised that they put them up
farther.
>> I haven't heard anything. I'm surprised
I haven't heard anything.
>> When you say down below your house, are
you talking about the box culvert, Cali,
or are you talking about another
culvert?
>> Yeah, the one right by Herring Brook
Road.
>> Okay.
>> But then they did the culvert up by um
>> Yeah.
>> pans. And that one has guardrails.
>> Yeah. So,
>> which is surprising because there's
nothing there.
>> Okay.
So, and you're are you in favor of this
adding guard rail to this? That's
>> Yeah, I don't I don't see a problem with
it. I mean, that hill when you come
around the corner, even there have been
times going up the hill coming back that
it's slippery and if you go anywhere,
you're going into the brook.
>> Okay. So that sounds like a good safety
issue to to also seem like we should add
some where Callie's talking about.
>> I certainly will go and take a look if I
can reach out there or Cali or I could
just take a look at it and see if we can
come up with a
>> Yeah, I mean I don't know. It just looks
like I'm surprised that they pulver put
guard rails up further and not
definitely down lower, but there weren't
guard rails there before, so that's
probably why.
>> Yeah. And as long as FEMA is paying for
it, yeah, it's a safety note. I think
it's
>> good. And again, if you can review up
above calories or below calories,
whatever it was, that would be good.
>> Okay.
>> All right.
>> Okay.
>> Good.
>> All right. So, um, you'll reach out to
me. We'll talk about the, uh,
>> creek stuff and then we'll
>> from there.
All right.
Sasha, do you want these signed copies
or and just
email
>> All right, so we'll go ahead and move
Mike's got a date tonight at 7:14, he
said. So
>> going to get going. The next thing on
the agenda is the truck bids discussion
of the board. So we had uh I think we
put out
like seven
seven um proposals and we got back um
two different stores but three three
different bits for a new ram. Um, one
was a 28 26
uh and then and from stone and that
these are fully equipped trucks um plows
sanders
what what we've uh put in the um
articles here. So there was a from stone
a 2026
ran 5500 uh $110,48
um the 2027
and this has to be ordered so this is
where it gets a little stickier um is
$108,270
so a little bit less um but we're
talking they think we could get that at
the end of December
and then we have one for Goss cost
$17,101.
Um, but he thought it would be probably
towards the end of February. Um,
the the
new order from Stone
that's
he really thought probably mid December,
but the end of December he he would be
pretty certain with. Uh, but here's the
rub. Um the current truck is been in uh
the shop for about 3 weeks. Um and
they've got some parts ordered for it to
come. Um, so, you know, right now we're
looking at a couple thousand dollar bill
there and then, um,
it needs to be inspected in November
before we would, uh, get a new truck,
you know, run inspections. Um, so today
I I originally was more leaning towards
one of the new orders. Um, but I reached
out today and spoke with uh the
gentleman at at Stone discussed the bill
that we have there currently uh the
truck that we have there. And if we
wanted to move forward with the with the
2026,
they would we would just walk away from
that truck. um no bill um
no other thing and we would have the new
one um within 30 days
um
>> for that price.
>> For that price.
>> So So we're getting nothing on trade on
it though or
>> Oh no, we're getting we're getting a
full trade,
>> right? Okay. But we walk away from the
current walk away from the repair and
then the potential
>> repair or whatever. to use it between
now.
>> No, we don't. It's not running.
>> Oh, I didn't know if they had fixed it
yet.
>> No, it's there's still parts on board.
>> Oh, I see. Okay.
>> And it's um there are brake parts. So, a
lot of things I'd say I just run it, but
brakes.
>> Yeah, that's kind of
>> So, my recommendation and I talked to
Martin today. He's not He had a personal
thing tonight to do. Um but we talked a
couple different times and u we both
agree that probably with the the 2026
brand new vehicle. Um it's just this
year it's here on the ground and we'll
have it within 30 days and we don't have
to spend anything else on the truck that
we have. Um
>> yeah, because it could be just keeps
spiraling.
>> Yeah, I mean already we got a couple
thousand um based, you know, on them in
order for parts.
Um and then if we used it and something
happens and
like you said has to get inspected,
>> right? Has to get inspected in both
places on the trade in
very close in their price and because
they're working on something and I don't
even know what the miles on it. It's I
think 9 years old and it's junk. So, you
know, they gave it a junk price which is
around 16,000.
So, so if everyone's uh tallying
questions at all, thoughts?
>> No, I think that would be better. And
I'm pretty sure for any new builds in
27, they're going to have um a different
emissions system setup.
And the first year of having a new
emissions system is probably not the
best route you would want to go because
if there's going to be problems, that's
where it's going to come out. So, you'd
rather wait a couple years to see how
it's going to work. So,
>> yeah, I think they have the death of the
Internationals and that came out. They
have that issue. So, all right. Based on
these conversations, I'd move that we go
ahead and purchase from Stone the 2026
Ram 5500 for 110,048
um trading in the current RAM that we
have.
>> Second.
>> Second,
>> Mike. Thank you for
any other uh if all in favor I
>> I thank you.
So Sasha, I'll reach out with him in the
morning, then I'll have him contact you.
Travis,
not this Travis.
All right. Um,
you know what? So, we can knock it off.
Let's
jump into old business. And
um,
Mike, you want to move down this way,
Mark? So, we can kind of
>> Yep.
It talked about the the library project
>> the town hall called the library project
but um
Donna I mean I I know um
>> what's that?
>> No I was but I guess with Ray's update
then we're we're going to see the FEMA
of funds then right?
>> Well it does it sounds like uh we are
going to see the FEMA funds though. I
mean, I think that's a that's a positive
big step,
>> right? Um I mean, we still have a FEMA.
We're still going to have a,
you know, um a match there's going to
we're going to come out with, you know,
$900,000 to a million dollars that we're
going to have to come up with.
>> Um but I think
I think, you know, Cory made some good
points tonight. Um,
you know, I think we've,
you know, we've sit on this or we have
sat on this and we've talked about it
and, you know, I think we're our hearts
are in the right place or is mine as far
as, you know, we're trying to save money
and not put people out and and such. Um
but you know maybe it is that time that
um you know with the right communication
making sure people know what they're
voting for what the con what the
benefits and costs are you know maybe
it's out of at this point. Um so all
right let the town decide what you want
to do with it you know um cuz everyone
has done a lot of work. Um
I I 100% support it. I want that
building and want it done well and and
functional.
>> Not do nothing. That's
>> right. It's certainly not a do nothing.
Um
>> um I mean at least to go through the
next step of seeing what
working with the finance committee and
seeing and and the Vermont bond bank and
let's see what the you know what the
number would be if if we borrow you know
this much. So did you take notes
from your meeting with the people and
Warren you and they said that you know
meet with the bond bank but what else
what do you I mean you know what other
things that well I did take notes I
don't have that with me but what they
did was well what we actually started to
do was um they did a lot of community
outreach with both people in favor and
people who are not in favor. So, you
know, they brought people into the into
the uh circle to to work on it from all
angles. That was one thing they said
that was important to to take the you
know meet with the naysayers and also
meet with people who were understood it
and were in favor of it. So, that was
one thing they did and of course they
had you know lots of communication. They
s suggested up they setting up a website
for people to see you know you know what
what and that's actually that's in
progress. We're about to that's almost
done actually. You know a whole bunch of
information about the town hall project
that people will be able to go to and
look at you know then we can get that
word out you know through front porch
forum and through
>> but I guess you know and I'm trying to
answer my own questions here as I listen
to you talk. I think that's what we have
to do. But I think the critical point is
our key. We do have the biggest we just
need to know what it cost.
>> Yeah. Right.
>> Right. So
>> what it would cost, you know, a tax.
>> So then Right. So then that way you can
get the people who are opposed and the
people who are for it something to talk
about. Right now it's talking about
>> I don't think there's anyone that
doesn't want it. you know, even if they
don't no one wants to pay for it. That's
the problem,
>> right?
>> Yeah. Yeah. I wouldn't think there'd be
like much opposition on the premise of
>> fixing it up. I should use it,
>> right? But it is I mean, I was in there
last week and I mean, like, I don't go
in there all the time, but the kids go
in there more than I do. I mean, it's an
old building. Like, it needs, you know,
>> it needs work.
>> Yeah. Uh so I think or my thoughts are
um and we did you know was the certainly
um when we had the the committee in here
um we discussed it so I guess we need to
tell you to do it with you guys but and
it been a little bit it's been fuzzy on
our part because we haven't had the
information and and I haven't pushed it
I I swear you know
>> maybe I should
you you know, and it's just one of those
things. It's like, all right, we don't
have a van left right now, but we need
to probably figure it out.
>> Yeah. Just to at least let's see what
it's, you know, we can't if December
comes and then all of a sudden Yeah. Oh,
yeah. We can let's figure this out. It's
almost, you know, cuz it has to be ready
to
>> be
by, you know.
>> Well, yeah. And to their other point,
uh, like the longer
>> they right, if if we if we wanted to put
a bond forward, right, the longer that
it's in out in the open, so to speak,
then people can educate themselves how,
you know,
>> cuz to put it out at the last minute,
then like people don't have time to get
the information
>> to uh discuss it. there's not time for
like the meetings like Donniey's talking
about. So, I mean, personally, I feel
like it at least makes sense for I
didn't know that we had to direct the
finance review committee, but it at
least makes sense for them to meet with
the town hall committee. There's no
reason they couldn't meet like whenever
made sense, right? To just whether
>> whatever the
whatever the recommendation is, right?
So, at least like if they're saying no,
you guys know exactly why. And if
they're, you know, sell
>> Yeah.
>> I would assume with someone from the
finance committee would meet with the
Vermont Bond Bank, you know, and and see
what they, you know, and talk to them
about the project and to show the costs.
>> So, I guess, you know, what I
I guess we do the end of the day, we
need the what was it going to cost? And
so I'm not sure how to direct the
finance committee or you guys to find
that, but I think so why don't we say
broadly this is we want to know what
this is going to cost starting in 2028
or whatever it is
>> or when the bond if a bond passes in
2027 and
>> whatever it is
it's this amount
>> you know a year or a month per in
someone's tax bill you know right
And
if everyone is well educated on it and
like I think a good point, Mike, it has
to be out there.
>> It it is uh like kind of like Cory's
other point about the time is like kind
of scary cuz like
the cost of construction is rising
astronomically
>> every Yeah.
>> So like if like I mean look at the whole
hardwood thing, right? When they bonded
it the first time and then they bonded
it last the second or didn't actually
put the it was like twice as much for
the same thing. And so it's like if we
wait
5 years or seven years,
>> it could be years,
>> right? It could be like twice as much
for the same thing and not right. We're
all not going to be making twice as
much,
you know, unfortunately. So, uh, you
know, relatively speaking.
>> Yeah. No, but when you start when the
numbers are like that, it's kind of
mindboggling cuz like it could go up
like a significant amount in a short
amount of time and then, you know,
Right. Uh I think when we know that you
know we give people the opportunity
you know even to Johnny Summers's
comments at town meeting last year maybe
when we really get those numbers we say
all right you know let's let's build
something new you know I don't know
>> move the sand pit build something new
>> so
so I move that we um direct or whatever
this is no motions here. Let's just ask
the the finance committee, you guys, to
get together at your earliest
convenience and try to come up with what
>> what it would be.
>> What it would be and whether that's
meeting with the bond bank or meeting
with
>> I don't know what it is.
>> Okay. The idea is to come up with that.
>> Is that fair everyone?
>> Yeah. Let's let's give it a shot so that
we can see where we are maybe by the end
of this month,
>> you know.
>> Yeah. I mean, I don't know how
>> No, not to say, but get an idea of some
of the costs.
>> Like I said, they're earlier you guys
are convenient. Um or by October say or
something
would be a goal. Okay,
sounds like a plan. I'll reach out to uh
Sher. All right.
Um
>> I think we need to be really mindful
with this also of the town's long-term
debt schedule.
I mean, we have a lot of debt. We have a
lot of loans out when you think about
that and the amount of interest on all
of those loans over the course of time.
I mean, you don't think about it so much
when you're voting on a truck here and
voting on a truck there, but you know,
>> 300,000 * 4 * 6 * 12, it
>> it adds up a lot in interest that people
are paying that the town is not is just
putting money away. So, I think in
looking at adding another in essence
long really long-term debt schedule on
there, that's something that we really
need to be mindful of.
>> Well,
>> and can we make a better plan for other
things,
>> Kelly? I think those are good points and
I think as we review this or the finance
committee reviews it or we present it,
has to be a full picture including that
stuff. Um to your point uh cuz yeah
sometimes it doesn't look too bad until
you look at everything. So we want to
make sure we're very transparent so
everyone knows what uh is going on.
>> Yeah. No, Kelly.
>> And I think they did a really good SK
they did a really good line
um I think when they came in and did a
presentation there's a there was a
really good chart that they gave us as
the board showing you know where the
loans were the interest rates when they
were going to get paid off then what
needs to get replaced on top of it
because I also think as a town there
have been times where we have put off
doing replacements because of funding.
and then we're at a point where we're
spending more money on repairs. So, kind
of that piece of getting on a schedule,
making sure that we're doing those
consistencies to get the better
tradeins, you know, to help out with
that. I just that chart was a really
great chart for us to have and really
look at cuz it it shows the picture. I
think Mike
>> Yeah, I mean it is like uh you know our
total debt goes up significantly and
well it goes up next year and then in
2028
again and then until 2031 when the chart
runs out it's about the same level. So
no it is a real thing like you're saying
Cali. So
>> um but I I think we should Yeah. So I
completely agree.
>> We have to keep that in mind. But then
if we wait 10 years, it might even, you
know, we should just get the picture
because if Yeah. I don't know.
>> We should at least have them reme,
>> right? Get the picture,
>> right? Figure it out.
>> Because if we say we wait till, okay,
this chart goes to 2031. Say we wait to
2032
and our debt schedule is still the same
as it is in 2031, you know, and then
we're adding it, but it's a bigger
number because the building's not going
to fix itself in the next seven years.
Well, you'd have to do something in the
next couple in the next year or two.
Just even some
>> right
>> some some repairs for sure.
>> Charman came across a grant today that
would help with that.
>> Great.
>> Yeah, there was something. I'm just
looking for it actually.
cuz there's two things on that capital
budget list that are not even thought
about yet and we are going to have to
pay on FEMA and there's that North
Moretown sidewalk if that's
>> well that's on here the North Moretown
>> projection or
>> uh well yeah project it's projected for
to start 2029
>> we just did payment on that
>> there's a
>> yeah that's on here too yeah Don so this
was for uh
between $50 and $150,000
grant and this is by uh
>> how much again?
>> Uh this preservation trust of Vermont
between 50 and $1 150,000. So it's real
money.
All right.
So, the other thing,
Kelly, what's the um name of the person
that sent us the email on the uh
on route two? You know, the little pole
off there. Do you remember? What was
that?
>> Mike, you had it, too. It was the the
volunteer is what I'm trying to get.
>> Oh, wasn't it about Caleb Dean?
>> It was Caleb Dino.
>> He was in here. Yeah, we should have at
least told him we were going to give him
a medal when he was in here.
>> Well, he was in here today,
>> wasn't it? Who was uh No.
>> Oh, that was Oh, okay. I don't I don't
know, but I just thought that was him,
maybe.
>> All right. So, um I was I'm just moving
along so I don't forget it. I I really
I'm pleased that that woman I don't know
if you saw the U email, was it Vermont
>> Robert Consery?
>> Yeah. Right. um just reminded us that
Caleb Dean's been
uh trimming and mowing and doing over
everything over there. And I think um
for several years he's been doing this.
Anyways, it came to my mind or what I
think of volunteers and um one we don't
unfortunately do a very good job of
recognizing some of those people. So
what I wanted to do on a on a monthly
basis and start with Mr. dean, but is to
highlight a volunteer per month and not
maybe one of the um or some of the
obvious, but they're on a committee or
things like that. We have a lot of
people. Um
the other thing I was Jim O'Neal for
instance, you know, who's done a lot of
um he did the railings, he did this, but
um if we and it can come from the select
board, um want to honor in this case
Dean for doing this this mowing. We give
him like a $25 gift certificate red hen
uh Moretown mug uh from the that we get
from the historical society. then you
know we'll make some plaque or not a
plaque but some kind of a certificate or
something um and we'll just try to do
that on a monthly basis so that we're
recognizing people and one of my hopes
is that once people oh I can do that or
I you know just more I think more
recognition recogn more we recognize
people excuse me um it's good for them
and it's you know it's it's deserved so
I don't anyone has any thoughts on that
>> just on the the timing of it. If we do
once a month, are we going to burn
through people too quickly?
>> That Yeah, that would be my I think I
was thinking more the first
>> 3 months. Yeah, quarterly is probably
good. The other thing
>> Well, just to make a a point of just
keeping it on the radar if we know of
someone, you know, whether it's a month
or two months apart in time, you know.
>> Yeah. But let's make sure we
>> some regularity feels nice against that.
>> Yeah, let's do quarterly then
>> and can put them in the town report too.
>> Exactly. That way. And so the other
thing and I forget these thoughts as I
as I talk but maybe instead of redand
which I think red is awesome is maybe we
do um first like a certificate to um
Lisa whatever the the greenhead cuisine
>> right something like that and then maybe
the local you know um
>> and then there's who else the waterberry
businesses
>> well you have also uh uh right here
fermentation uh Yeah.
>> So, if we could do those, you know, try
to keep the money in town both ways.
>> Um,
>> well, there were a bunch of I mean, I
don't have the list with me, but there
were a bunch of local Morttown
folks, businesses, uh, that donated to
the bingo event, you know, that, you
know, right prizes. So,
>> business we probably don't know about or
really
>> Yeah. No, there were some, you know, you
know, like uh Brian Moore with, you
know, gift certificate to to the for
plants and there was,
you know,
>> Yeah. So, let's
>> I have I got the I didn't I could bring
the list to folks, you know.
>> So, if we're all good with that, we why
don't we um
we'll write something out. We'll put
something out for Caleb Caleb Dean.
and uh
>> he's got an existing relationship with
red hen. So I think not being red would
be a good idea.
>> Okay.
>> Very good. Yeah. So we'll do something
something different and uh you know that
recognizes it's both the business and u
person as well. And Sasha and I already
talked about it. She said she'd help out
with the project with it as well. So
>> okay,
>> we can do that.
>> And then in the same vein we had our 20
year employee. Is that right?
>> Yes. Thank you.
>> Cuz I think Yeah,
>> cuz we were talking about that. I said,
you know, I apologize for not
recognizing I mentioned Friday. Um and
then things got busy and we needed to go
ahead. Um
>> I don't I don't have a plan.
>> Is it Is it Martin? Is that right?
>> No, it is Rodney.
>> Oh, Robbie. Okay.
>> Rodney. Um, yeah. So, Rodney 20 years on
what, the 28th?
>> Yep.
>> Um,
put up with everyone here in town for 20
years. I mean, my god, I think he's done
well. Um,
and us putting up with Rodney, too. Uh,
but Rodney's a great uh equipment
operator, truck driver, um, and just a
good person.
>> Great talent asset.
>> Yeah, he's just a he's a good person.
That's what we we look for. Um, so yeah,
let's make sure we we shout that out and
if we can come up with something for for
that. I think that's a good idea.
>> Yeah, it' be nice to show them
something.
>> Yeah,
that's for sure. All right. Um,
so why don't we go ahead and get back to
reports and communications
because I still got 14 minutes
based on uh,
>> right?
>> So Sasha, what do you got for us here? I
have a email from Dick Bell tonight
about his
reimbursement for or his reimbursement
for health officer.
>> Uh he's asking for an increase this
year. I don't know if that's something
you guys want to do. It's normally $300.
He's asking that he get $600. And
I've got the email here if you guys want
to see it.
Why don't you go ahead and um
I was going to say send that out, but
please reimburse me for shells off of
the channel. A few years ago, the chair
asked me if I wanted to increase my
reimbursement. I would like an increase
to 600 a year, which is what AI
which is what says IIA few a few years.
I don't misspelling there. So, the chair
asked me if I wanted an increase in my
reimbursement. I would like an increase.
I was repeating the sentence. Um,
excuse I can read here, folks. It's just
Anyway, if you'd like an increase of 600
a year, which is what I've been getting
from the town of Ducksbury, please have
the board consider this request. And
this is for this year here, Sasha.
>> Yes. Hasn't been paid 300 yet.
And um I think that's probably I mean
obviously it's 100% increase but he
hasn't had um an increase forever. And
um
what's what's everyone's thoughts? I'm
fine with it.
>> And what exactly is he doing?
>> He's he is the health um health officer.
So he'll he goes in if we get complaints
on anything, you know, we have a lot of
frequent flyers that he goes to uh with
garbage that are out that's out. Um
when we were doing the Piaza building,
he spent a lot of time in that. Um and
he did, you know, orders there. Uh so he
spent time at that actually at the port
as well. So he's
>> a lot of work.
>> So yeah, there's a lot of work
sometimes. I think some years it can
probably, you know, waxes and wanes
where you may just, you know, go and
look at a few um dirty backyards with
garbage and tell them to pick it up. And
then there are other times when you get,
you know, in the right harassed and and
it's something we need and he does a
good job and probably could use the
money.
>> Yeah. No, no.
>> All right. So, I'm Sounds good.
>> Is that all right? So, I move to uh
increase the board the pay for the U
health officer from 300 to 600 a year.
Um
uh starting now at 226.
>> Second.
>> All in favor? I
>> I
>> Thank you,
Ash.
And then I have that new Boys and King
amendment to the sidewalk that I had
from the last meeting. You spoke to
Cherylyn about it in between.
>> Yes.
>> So, this was the amendment that we had
that they had wanted to change. And I
had um uh really wasn't clear on it, but
anyways, it's a $7,000 increase, and I
think I had said at the time it was much
more than that. Um, and it was approved
um by Ken uh looking at the amendments.
So, we'll just go ahead and sign it.
And
>> Cherylyn's asking for permission to have
a rabies clinic. We were She was
thinking about here, but then thought
about maybe the basement of the town
hall on October 24th.
that way. Rain or shine, she there's
cover for for it.
>> It's the first time anybody's done it,
so it's a new thing for more town.
>> I think it's good. I mean, it's the
space. Is that the best space for it? Or
would the best space maybe be the fire
station, you think?
>> Is this like people can come and get
their dogs animals vaccinated for free
or something? Or
>> uh lower?
>> Yeah.
>> And the ar Yeah. check out. It's
definitely on the fire station. I'm
thinking it might be just easier
>> Yeah.
>> in and out. Um
>> cuz you have to you better go down the
stairs.
>> Stairs on the side door anyway. So
>> parking sort of an issue
place, right?
>> Um we could direct people to park here.
>> Go down our new sidewalk.
>> Yeah.
How many people or Cherylyn's on? But
>> we don't know.
>> Yeah, this is the first time.
>> Is this like also cuz the state's seen a
big uptick or whatever or
>> I don't know. She's had this vet bugging
her.
>> Great. Let's go.
>> Yeah.
>> Yep.
Um Paula Woods would like to be
reappointed to the DRV.
>> So moved.
>> Okay.
>> All in favor? I
>> I
need to do a second.
>> Don second it.
>> Something wink at me. Thought that's
what that meant.
>> All right. Um,
we had
back on May 18th,
you guys approved the turnout year for
Steen for the fire department. We didn't
get any specifics in the
audit because we didn't really have an
invoice at that point. I have an invoice
for 21,480.37.
The article was for 10 grand.
Um,
the motion was for capital reserve
financing, I believe. And I'm just
thinking that we need to have
clarification on that. He could take the
148037
out of his maintenance budget.
because there's plenty.
Um, what would you guys like to do?
>> Um, Sunny,
>> um,
why don't we Can you We have to make a
decision on that tonight. Do you need
that tonight?
>> No, but I do need to pay it soon.
>> Wasn't Was it two sets? Like, cuz we
>> four sets.
>> Yeah, four sets. So that's why it's 20,
not 10.
>> Yes.
>> Right.
>> Yes.
>> Yeah.
>> Because that's right.
>> Yes.
>> And so Sasha, the question is where do
we take the money from?
>> Yes. Do you want it all taken from the
capital reserve to pay for it? So
there's no financing
>> because it's such
>> But what was the 14? You talked about
>> the 148037
is just it's the whole bill is 21 480
37. the 14 8037 could come out of his
his line items.
>> There's that much there.
>> Well, remember I
>> Well, he upped it at seven grand.
>> Yeah, cuz I'm going to I'm going to
bring that up. We have some work still
we're trying to do there. Some
>> All right. So, let's just hold for a
couple days on that.
>> Let's hear from Don and then let's you
and I circle and then figure that out
and then we'll present it to
>> circle back to that.
>> Y all right with everybody.
All right, Sasha, continue, please.
>> I think that's all I have for now.
>> Sam, how about you? Any uh reports
communications announcements tonight?
>> Uh I I guess question for Sasha. I know
we've talked about bringing in somebody
to give a presentation about the lot
tax. Uh where I thought that that was
scheduled
>> 9:17.
>> Thank you.
>> You're welcome.
>> So, that'll be the next one. We're going
to look forward to that. What was it?
>> It's the Oh, can you help me with the
guy's title?
>> It It's the people who gave the
presentation in Weightsfield that was
helpful to convince their select board
to move forward with putting it onto the
ballot of the lot tax in Weightsfield.
So, he's going to put together a similar
presentation.
>> What is it? I'm not hearing
>> the lot tax. Local
>> local tax.
>> Oh, yeah. Okay. Yeah. So, he's going to
put together a similar presentation for
us to let us know what sort of value it
could bring in for the town. We're going
to be presenting that in a couple weeks.
>> Is he going to give us the
like the breakdown cuz like the the
difference between us and Weightsfield
is
>> we got a whole lot of this business. We
don't
>> like So, right. So, we're just almost
like Yeah. Yeah. I mean, is he going to
give us like what would potentially cuz
if it's all like if it's going to be
mostly more town people, we should just
raise our
>> budget and the same, you know,
>> but it is we do
>> I'm not like a he will come in and do
that. That was my understanding from
correspondents is that he's going to
come with a little bit of an estimate
for us.
>> Yeah.
>> So, we'll see what he says. It could it
could not make sense,
>> right? Oh, yeah. No, no, I'm just Yeah.
Yeah. Yeah. Yeah. Cuz theirs was like
whatever 70 whatever the numbers were.
There's a big number was going to get
paid by
>> people out of towners.
>> Yeah. People traveling into town.
>> Yeah.
>> Yep. And we do, you know, those people
do stop in more town, too. We do have
the general store, right? People are
stopping and getting cash.
>> There's not it's not a zero number,
right?
>> But it's worth it's worth.
>> Yeah. No, for sure. And also would he
have people often talk about like the
Amazon in their tax on that and he does
he um
>> he can explain that too. You know, it's
just any any purchase as long as it's
not an excluded category would be
subject to the new tax.
>> So yeah, a lot of a lot of all those
packages that are coming in, the stuff
that people used to buy in town because
we had town stores, uh we'd have a way
of collecting tax on them. But I'm going
to let him give
>> Yeah.
>> Would that would he would that also um
>> be in that discussion maybe with him or
some you know I wonder if you know some
of the short-term rentals if that's you
know I know tried to launch that and
they had a whole spent a whole thing on
listing all the properties and they
haven't gotten people to really list and
they're trying to have a tax on you know
not a tax fee.
>> Yeah. I think fields in the process of
getting something together that they're
going to present and I think it might
make sense for us without resources to
wait for them to go first on that and
then see what they're doing.
>> Yeah,
>> but that does administrator which I
think we should keep pushing forward.
>> Yeah. Well,
that's
we can just jump onto that for a minute.
So,
>> yeah. You want to go ahead on that?
Well, you know, you know, Sammy answered
that he could be available to
>> to meet with Kathleen Ramsay is her name
from BLCT. Um,
but then another email uh that she
forwarded that I sent to was the um was
talking about how Middle Sex, if you got
a chance to read that, how they just
recently hired.
>> Yeah. And they actually I guess before
you know they had they had formed a
committee of to people to work on it and
figure it out and then vent it and do
you know they got the applicants made a
recommendation to the board you know
it's in that email. So whether we go
that route maybe after we
>> we're a hybrid of some of that I guess
so
>> at this point we need you know two folks
two people from the board to meet with
Kathleen. All right. And Sam, you said
>> and it's a matter of, you know,
>> yeah, I could make myself available
depending on when it is or
>> that would be awesome. Like if you could
>> Yeah,
>> cuz you
>> It's just like an hour meeting or
something or
>> I'm I'm hoping so.
>> Yeah.
>> Yeah. I mean, maybe you could I'm sure
she'd come to here or you could meet her
in Mont Pillia or in Middle Sex maybe,
you know, at the local or something. I
don't know.
>> Yeah,
>> something like that.
>> Okay. Yeah. Know, I think that's
something again. I
>> mean, so you have you have her email, so
you can
>> Sam could probably respond to her now,
right?
>> Yeah.
>> Yeah,
>> that's that was one that you forwarded.
>> Yeah. I mean, you have for Yeah.
>> Okay.
>> We'll figure out a time.
>> Yeah. Cool.
>> That'd be great.
>> Nice.
>> The goal there just being it's come back
to you guys and let you know what we're
hearing.
>> Yeah. Yeah. and what she suggested how
the process and stuff I would think is
what she's going to do.
>> Good time. Why don't we uh see how
you're all set?
>> Yeah.
>> Okay. So, uh facilities uh Jim and I are
we're trying. That's hopefully a town
administrator will get further than we
are, but we're getting there. So, um,
the, uh, history center. So, we put in,
uh, if you remember, we budgeted, I
think, $12,000 to replace the roof
that's shot. And I've gotten two quotes.
Um and um
for and the the quote that I have that I
would recommend that we go with is from
Solar Zachs
which is Zach Mosto. So at least it's a
local business. I do have another quote
from Mike Gouki who I've done a
tremendous amount of work roofing work
and his is his um
his bid is for 135 and that's a metal
roof and Zach's with as with shingles
and the shingles have like there's a
50ear
guarantee and you know anyways we've
kind of edited out that would be our
recommendation to go with Zach on that
um
and uh he can produce the W9 and the
certificate of insurance and all that.
So um and I do have a a printed copy of
Mike Goki's uh quote too. So we have it
for the record that you know
um wants to
>> So that's that. And the the other piece
of work that would get done there with
some volunteers is behind the building.
There's a bunch of brush and clean up
that needs to be done. You know, just
clean, you know, some,
you know, we'll get bird's eye
consulting down to cut some trees.
>> Yeah. Work get crew down there, work
hard.
Yeah. And so then next year the thing to
consider on that building would be
probably next year would be um to look
at whether we're going to you know paint
it and just paint over it or spray it
and whether there's lead paint and all
that. I mean that's a that's another
time another discussion.
Um,
so as far as the fire station goes right
now, um, I don't any have any numbers
yet, but I will tell you that we should
leave some money that we put in. I think
we did put seven in. I'd have to go back
to look at what we put in. But, um, it's
not going to cover what we need to do
with the fire station. But one of the
things that we we're working on
is the entrance door. was, you know,
>> did you Yeah.
>> So, um, we're getting a price for that,
which would be the new hollow metal
frame and the door. And then I know
there was some discussion about maybe
what the hardware will be. So, we'll
have to talk about that as we get, you
know, a little more specific with the
details. And including in that door
replacement would be um oh I had a
picture of it is a little roof over the
door cuz the gutter way up high is not
work. So you know it' be just a little
slanted roof tied back you know like
sort of like this kind of thing over the
door and tied back like that.
So, um, and then, you know,
I've se Stefan's been really busy, but,
um, when Jim and Zach were down there
looking at some stuff there, uh, cuz
Zach's got a 40ft ladder and, you know,
there's still the vent in the back way
up at the peak that needs there's a leak
because of that, but getting up to it.
They heard I think we have some pests
there again. So, I'm surprised we
haven't heard. You know, they think
there's some squirrels up in the That's
not squirrel.
That's That's That's
>> I don't know how to say that's how I say
it. This is squirrels in our attic. I
know. That's all words.
>> Yeah, we all have words. Um so, we'll
need to We got to work on that. And then
I remember Stefan saying also that one
of the garage doors
Uh the motor shot. So
>> I think it's already been replaced.
>> Uh has he? I don't know.
>> Yeah, I think so. Hasn't that been?
>> I don't think so.
>> I don't think we can get the door up
without it, right?
>> No, I think they've been opening it
manually or something, but I don't know.
I I'm trying to I'll get down there and
meet with Stefan shortly. So, and then
there's some building patching to do
some of the siding
and we'll see if we can I'd like to see
that get done this this fall, you know,
here we are in the fall, you know. And
then one last uh two other items in this
facilities discussion is um and I don't
have all the different quotes that we've
got. You know, we got uh we had uh
Dubo King uh the engineer um
>> Ken
>> what? Not Ken, but is it is it Dubo
King? No. Uh
>> Art Creek. No, that they did they came
and did an engineering study for us on
the they came in to see what would be
some of the best solutions for the
moisture problem at the town garage and
I'm having a you know I could try to
find who it was that did that for us you
know we they did it anyways in their
recommendations one of the things was a
really simple one instead of the
adding a unit up in the ceiling and
vents and this and that was just to get
a dehumidification unit.
And so one of the prices I got was from
Gillespie
to supply a mo, you know, it's a 600,
you know, the specs here.
>> Yep.
>> But it's a mobile
uh unit that you would just turn on. It
has a 30ft drain line and it's, you
know, it's $5,700. They they've sort of
they put a filler out for when it would
be available. I don't think we'd even
see it till November. Um,
and I, you know, I I'd like to see if we
could, you know, uh, vote on that today
or something cuz I'd like to at least
tell them to see if they can just make
the order be a while before we see it.
But, um,
>> and that we have the money in the budget
there for
>> Yeah, we put money in the budget for
that. Yeah.
>> Oh, yeah. It was to Boys and King. Yeah.
They did this whole study about, you
know, some of the solutions that we
could do and this seems to be the the a
solution and the least the less of the
cost. I mean I got a estimate from peak
at one point that was 50%.
>> Yeah, I think I was remember that that
was
>> Yeah.
And that was for adding a whole bunch of
unit and electrical and you know but
this would just be a plug-in unit.
>> Well, I think this is it's in the
budget. It's in the recommendations. I
don't think there's any reasons why not.
So, I'll move to uh go ahead and uh
contract with Gillespie for $5797.14
for the um Quest High Efficient Dry 195
dehumidifier with 610
CFMs.
>> Here we go. And I've gone over with Mark
as well.
>> Is there a second?
>> Oh, I'll second.
>> Thank you. All in favor I. I
>> I. We've gone through and followed the
procurement policy and purchasing policy
for it. Put out all the bids,
everything.
>> Yeah. So,
>> to everyone who needs to.
>> Yes. I have uh a couple of different
bids for a a couple of the of the
scenarios that were outlined in in the
boys king's
um recommendations that I'll put
together to bring to the office.
>> Yeah. Yeah, cuz I think you had one at
50,000. There's all sorts of all over
the place.
>> All in favor? I
>> I
>> I. But then this is like Well, I guess
it could be semi- longterm, but then
eventually like we still need to
>> or this could be this could do.
>> This could potentially kind of fix it.
>> And then from there when we're seeing
that that's working,
then there's a lot of other work that
has to take place on the building. you
know, repairs the eaves from some of the
moisture damage that's, you know,
rotted. The building, you know, there's
some exterior siding that needs to be
replaced. The building needs to be
painted. There's some grading on the
exterior that needs to be done cuz
there's water damaging the the, you
know, bottom 12 18 in of the base. You
know, there's there's a bunch of stuff
there for sure.
But Cali brings up an interesting point
that I I'd like to ask because I was
looking at what Cherylyn sent us about
that we need to make some
uh this I guess it's based on the FEMA
stuff, but this some policy purchasing
it's I guess it's the purchasing policy
or or is the purchasing policy on
steroids or I'm not sure like that.
Yeah, I haven't had I I I kind of read
through it, but the only thing I'd like
the town to consider
um or at least
like right now it's you got myself and
Jim trying to get you know work on not
even common the town hall but four
buildings because even this one needs
work and you know we're we're doing the
best we can but then one of the
challenges is is finding the people to
do the work. Like in other words, I'll
probably he hasn't been able to get
there yet, but Spencer Doom Dumis who
lives in Weightsfield who's been does
doors and frames and hardware, he's been
doing it for years and years, you know,
a local guy. I'm sure anybody who's had
any problem with their locks has called
him. You know, I certainly have. But,
you know,
my example or then there's
>> So, are you looking for approved
contractors? Is that what you're saying?
>> Well, I'm trying to say is that some of
these smaller repairs to some of our
buildings, it's going to it's just going
to be more efficient and easier to try
to, you know, get, you know, one person
and goes, "Yeah, I can replace this door
and frame you, it's going to be this
much, you know, and and instead of
having to get two or three prices and it
just will drag on, you know, I mean, it
just
>> I mean, the amount of I think you
>> the amount of time, you know, how much
time Jim and I have, you know, Maybe
when we get a town administrator
someday, some of these things will end
up being in that person's purview, you
know, but we're, you know, just trying
to do it as volunteers basically.
>> Yeah. I think you talked about this
winter, Donnie, that like for these like
maybe not buying equipment, right? Like
the dehumidifier like
>> the rail like how you going to get
>> $1,000
$1,000 project. It's like
>> right,
>> you know, like Jim went down and put a
temporary railing in. You know,
eventually, you know, I got him, you
know, he spent four hours and he bought
hundred and something
dollars worth of material and I got to
get him to write something up because we
should reimburse him at least for for
the the material.
>> But, you know, just finding someone to
have done that, you know, at least we
got it done cuz the sidewalk was being
done. I mean, you take the railing down,
you know, with the new, you know,
>> I think maybe uh just full review of and
I mean kick that can down what a year
>> many of them but uh the purchasing
policy
>> you know and because we have we've I
mean that was established I don't know
how many years ago 20 years ago things
have gone up exponentially
>> and our policy has stayed the same um
obviously there's reasons behind those
policies is, you know, trying to
make sure that we're not um spending
where money where we shouldn't. But I
agree, we need to I think between maybe
tweaking the amounts and the things that
maybe have to go to what we do and also
maybe um approved contractors. I mean
there's you know the state has them the
you know there should be all right you
know a couple in each like the gas and
oil you know Gillespies and suburb
whatever or whatever happens to be
something like that
>> something that's vested or vetted um and
people you know
>> with some some people who are from town
who you know yeah I can get that job
done for you they live in more town
>> you and it's going to be this much and
you know you look at the numbers and the
breakdown you go yeah I mean it's it's
fair you know
>> yeah cuz I know you know like UVM
uh
you know had a policy for like
excavation projects under a certain
amount like were no bid cuz it was like
small you know so they could do what
we're talking about
>> yeah I mean you got to be able to act I
mean to put a door in to spend you know
two months Let's figure out who's going
to put the tour in, you know? We just
have I just, you know, boom. I just want
to get it done, you know?
>> Right.
>> Well, I think the thing with these
policies is that it is also they're put
in place based on FEMA and grant funding
and
considering the amount of money the
town's going to be looking at a single
audit. And when they look at a single
audit, they're not just looking at, yes,
you got the money and you put it where
it's supposed to be. It's that you
followed the policies there and there
set policies and adverse findings on a
single audit are not fabulous at all.
That affects all of your grant funding,
not just federal, it affects your state
because it's I mean the single audit is
looking at all the money you have coming
in. So these policies are put in place
so that you are compliant with any of
your grants.
And if you're not and you get that
adverse single finding, I mean, you're
not gonna get that grant funding.
>> Yeah. I think we're we're actually
melding two things here. We're talking
about some grant funding and some
recommendations on FEMA policies and
spending that way. And then just our
purchase policy in general and on other
issues that don't involve FEMA. So,
>> but these grants look at your purchasing
policies,
>> right? I understand. Um, but we can have
more than one policy.
>> I I don't know if it can be Yeah. If it
can be a thing in the policy that you're
allowed to for some XM there does say in
the FEMA policy thing up to a certain
amount, right? I think it was $2,000 or
something that you'd be that you could
go ahead and do something. But, you
know, any repair,
most repairs we have in any of our
buildings are more than that, you know.
So, I mean, I I don't know. I'm just
>> Right. But when FEMA's doing um audits
on a on a project, they're not going and
looking at or spending
>> to fix a door.
>> Fix a door in the fire department.
Sorry.
>> I don't know. But maybe Cali with Cali
saying that they maybe they look at
everything. I don't know.
I mean it's not with that but it's also
you have the policies in place. These
policies go with grant applications any
grant application. So
these are the policies that you are
following one way or another. Doesn't
matter if it's grant funding or somebody
fixing a lock. When they did the audit
this year, they pulled they gave a list
and it was mostly bigger invoices, but
they did have a few different things in
there just making sure that things were
in check like the invoices were signed
by an authority and and that type of
thing just matching our purchase policy,
>> right?
>> Yeah. They they look at that as well
like are you following following your
policy? When the auditors come in, they
sit down, they spend a day and they go
through all of your policies. Are you
following this policy
for everything you do?
>> Policies, it's invoices, it's
everything,
>> right?
>> So, it's not just it's not just, you
know, helping somebody out or doing
this. It's following that policy you're
using for everything. and everybody's
looking at it,
>> right? But if we update the policy and
then we follow the updated policy, then
we're all good moving forward.
>> I would be mindful of updating the
policies to make sure you're following
what it has to be for everybody because
if you if you've got pieces in between,
it may not become compliant for
something else.
>> Sounds like
>> which then puts you in that you're
falling out of compliance for something
else. M.
>> So that's where, you know,
>> you have to look at the FEMA policy and
you probably honestly are going to want
to go with the more restrictive policy
>> because
different
agencies, different places have
different regulations. And if you are
stricter
then that's going to help you out in a
wider
looking at wider things.
So
but it's not just it's not just the
grants. It's not just FEMA. It's it's
everything tied in with that. and
even updating it for the smaller things
that we need to do can affect the bigger
things that we need to do.
>> No, I certainly agree. I don't think
it's a haphazard
uh activity just to go in make a policy
easier for us as the vend or the vendors
or or or us. Um, but I think it's it's
our um we should take a look and just
make sure the policies are up to date
and um just that they work for us. I
mean, if policies aren't working for us
um you know, we need to take a look at
them and see, you know, how we can make
them work or um or or change them as
long as they comply with all federal and
state guidelines to compliance.
So,
>> okay. Well, I'll carry on trying to at
least get two prices for whatever I
whatever we do,
>> right? I mean, I think that's
>> So, back to the roof. I mean, uh,
can we go ahead with this with the roof
of the history center? That's this right
there. I do have two calls. I do have to
get all the W9 and certificate insurance
but
>> right I mean because again this needs to
be
>> yeah that I think we're good with that
we vetted it what they're going to do
and they're going to add some bracing
to the existing joist
that Mike
>> yeah I already kind of looked at it
>> the the uh there is a picking the color
of the shingles. I don't know if any
anybody here I was going to see if
Denise and Mary wanted to maybe pick
them, you know. Um, and there you go.
And I think it'll be nicer in uh using
ash doll shingles personally, especially
with the guarantee on the material for
50 years or something like that.
>> I just did the same shingle in my house.
>> Oh, there you go. Oh.
Yeah. I mean, looks fine. I don't see
anything.
>> What was the other one? It was um
>> 13,500.
>> Yeah. For a metal roof.
But, you know, this act is, you know,
12 14 $1,300 less.
>> Yeah.
>> So, you have any questions or thoughts?
>> No, I think it makes sense to move
forward with them.
Oh. So, I'd like to make a motion that
we uh accept the the bid from uh Solar
Pack to replace the roof on the uh
history center um for $12,
>> $230.
Is there a second?
>> Thank you, Sam. Any other questions?
All in favor? I
>> I.
All opposed.
She's not there.
>> Kelly voting.
>> I'm gonna abstain.
>> All right, John. Go ahead.
>> Okay, we'll get that going.
>> Anything else?
>> Uh oh. Anything else? Uh
the town administrator. Uh
well just something to think about with
the crosswalks now just done and um as I
mentioned u
the last meeting they these crosswalk
flags.
>> Mhm.
>> So if you want to just look at them
they're 200 it's called you could go to
the website it's called see me flags.com
and you can see them in live and in
action. In fact, um I saw my wife use
one in Wville
crossing the road to meet me across the
road from the library and she traffic
was coming. She got the cross, grabbed
one of the flags, waved it and
>> people
puts it on the other side.
>> I think we just need it for maybe the
one by the post office in the store, you
know, there just come around the corner,
you know.
Um, and then I I have asked Cherylyn
along those same lines like she is
looking for it, but at some point we got
to fix the radar units in the village
cuz they're, you know, this one's spotty
and this one I tried to get fixed, but
Scott from whatever the company is,
they're uh
safe something.
>> Work safe.
He felt like that by the time they spent
the month, the the time and energy to
fix it, you know, what it was going to
cost to fix it, it wasn't going to be
worth it. It would be, you know, in the
long run, it would be better to replace
it. So, um I guess we need to do that
with a grant probably or some some of
them get some money. So, the grant and
we'll probably have to put some money up
as well. But, um hopefully we can get
that at some point. Um
then another we had was the the u giving
permission to friends of the Mad River
to collect native seeds.
>> Mhm.
>> And I didn't see anything. I I would
think that would be fine, you know.
>> Mike, what was she? Did you see that?
>> Yeah, I responded to Sasha. Uh I just
Yeah, I don't I don't see any problem.
They said they're only taking a small
amount anyways and
>> I I don't see any issues.
>> All right. Yeah. So Sasha, you can reach
back out to where that wants to.
Um
>> I'm assuming they're just doing it for
like wild flowers and stuff and
>> Well, yeah, it's like it said in their
email. No, and trees too.
>> Oh, yeah. I think so. Yeah. I mean,
>> species. Yeah.
>> Um and then I don't know if we'll get
this thing, but we did get an email that
we're supposed to do something with the
CVPC regional planet maps. I'm not sure
what we're supposed to do, but we're
>> Yeah, I saw that. I just saw that email
and I didn't really get that deep into
it, but we got to keep that on the radar
apparently.
>> And then to give a just a quick we we
did have our meeting at Pony Farm, Mike
and Martin and I
um and that went well. The folks there
Phil and uh
>> Angie
>> Angie, thank you. you know, we we you
know, they've got a good understanding
about what needs to happen now in terms
of parking and being responsible.
>> So, do you guys measure things out or
what?
>> No, not so much. But the next step we
decided is and I've reached out to
Michelle Redmond is to meet with the
state because um apparently Martin was
saying the state did a lot of the work
there at the end of the road and over
towards there, you know, the way the
road comes down and at that angle and
all that. And so I've reached out to
Michelle Redmond. She's going to bring
someone from Vermont Traffic Control.
Maybe Chris Hunt is going to come as
well and um we're going to meet with uh
we're going to have this meeting with
with Beef Trans when Martin gets back.
He's going to be on vacation. So at the
end of the month hopefully um we're
going to meet with them
>> and see what what can be done with that
intersection because there's a lot more
issues than just their parking there
when people come onto that road and
stuff. And it would be really good to be
proactive about it anyways because with
the Mento uh
>> the Mento road bridge that being
replaced and then in 2829
the state's going to be replacing the
bridge here at Dallas Brook
and that the the wrap is that then
they're going to be using Pony Farm.
Then that's why Meadow Road they want to
try to get that bridge done before they
do that. So, you know, it's it'll
>> Well, actually, maybe with that halt
going on, that'll push them to help.
>> Yeah. No, that intersection. Yeah.
Right. It would be smart to sort of look
at at that intersection. Yeah.
>> Right. Yeah.
>> But yeah, we left and then they're on
the same page as Martin.
>> Yeah.
>> So, that was and then that was the most
important thing. And then we're going to
meet with the state
>> now. Now, we'll meet with the state. So,
we'll let you know when that meeting is.
>> Perfect. Thank you for getting that
done, guys.
And uh yeah, that's about that's about
it,
Mr. Mike.
>> Um I don't think I have anything new
except I was going to suggest some
things we could take off of old business
pending.
>> All right. Uh
I don't know. I think we could take off
the whole bottom line because we just
are saying we resolved pony farm parking
issues
parking ordinance and I think we already
did the land use recreational land use
policy. I think Chris crafted that like
this summer.
>> Y
>> was the parking ordinance updated that
it needed to be rewritten.
>> I don't know what needs to happen with
the parking ordinance.
>> It needs to be updated because it wasn't
it hasn't been done since 1978.
All right. So, let's take a look at
that.
>> On there,
>> and then recreational.
>> Yeah, I think recreational land use
policy can come off because they crafted
that. We agreed to it.
>> Uh, you know, I almost seem to feel I
guess buyouts on Route 2 is ongoing,
>> but that I think condensation of the
town garage. We just solved that. Take
that off the list.
>> Bam.
I'm here to give you an update on the
bias if you're interested.
>> Hey, Carol, come on down.
>> Then maybe we can take that off, too.
>> No, you can't take on this.
>> We can take maybe the we put town garage
for repairs. We probably should keep
one. Well, it's fine. We can just keep
it in the facility.
>> Yeah.
>> Okay.
>> Okay. Um, if you've driven by, you've
noticed that one house is gone and it's
all nicely seated and the grass is
growing up. There three Gamble Road
houses are going to come down starting
sometime this week.
>> The one that's before the engineering
company there. Those three.
>> Those three. Yep. Um,
Larry Westover's house has been closed
on, but I don't know exactly yet when
that will be. Is he taking that trailer
out of there? What's happening with
that?
>> The trailer? What? At Larry's?
>> Yeah.
>> I don't know. I haven't driven by
lately.
>> I mean, you say closed on. I mean, the
the buy
>> the the town owns his house now, but the
demolition hasn't been scheduled for
that one.
>> Do
Do we know where any of these folks are
going?
>> I know where Larry's going.
>> Larry's got a house.
>> Larry's got Yeah, Larry's got a place to
go.
um went up there by
>> Steve went to Florida
and the other three were rentals. So I'm
not sure where well the one was had been
empty since Irene. The other two I don't
know where those people moved to
>> but they found their
>> they there's assistance for rental
relocation there.
>> So those three are going down. Um,
Larry's is now the town's I don't know
when the demolition is. The Schaer's
House is closing in December.
They're moving to Pennsylvania.
And then the three Douglas properties,
we don't know yet if they're going to
participate.
>> They have what?
>> Douglas properties. They have until the
end of the year to decide. Um, but the
other thing I wanted to let you know is
I don't know if you remember that we've
been in touch or the National Park
Service kind of reached out to us or Bob
Blahett reached out to them and we've
been meeting somewhat regularly. They're
kind of tying it in with a lot of um
Waterberry bike path planning and
they're looking at the Gamro Road
property closest to the testing property
as a potential put in pull out place for
the river because that's got the best
access going down. They put together a
website. They've put together a whole
bunch of information. We're going to
have some of that. The planning
commission is going to have some of that
available at Morfest just to kind of let
people know what's going on and get some
feedback. But the one thing I wanted to
bring to your attention to kind of keep
thinking about or start thinking about
is what level of maintenance the town
wants to do on those properties once
they are green space
and what kind of coordination I should
be talking to the National Park Service
about with maintenance for if they do
put in bike trails or
river access or
>> the crossont Montreal, the director of
that has re, you know, called me, you
know, reached out to me because he was
also talking about the section that's
going to be part of the whole Mad River,
you know,
>> right,
>> path card or um
>> No, that's interesting. Now that I think
about it, I don't think the I don't know
if the Cross Vermont Trail people have
been part of these conversations. I'm
surprised cuz thought I thought he said
he was
>> the canoe people.
>> Yeah.
>> Why am I not thinking?
>> Because you know you come off a lover's
lane and then you're on route two and
there could be some opportunities to be
off route two across from there,
>> you know. So,
>> well that's
>> maybe I should, you know, reach out to
him and tell him to maybe just give you
a call. Yeah, I have him reach out to me
and let me let me see if he's been in in
with the National Park Service
conversations.
>> Okay. And so you were thinking like in
terms of mowing or just like that type
>> Yeah, that's what I'm wondering. What
>> what do we want those places to look
like?
>> I feel like unless it's like turning
into a river access, we'd almost just
let it just let it grow.
>> Let it grow.
>> I don't know. Maybe a lot of people have
Yeah, we could plant some trees like you
know there are like and I don't keep
super in touch with them but like there
are like
>> you know I think we can get trees from
like branch out Burlington and you know
our
>> friends though and that and then there's
even like some other random stuff that
comes across my email sometimes. So
>> we could do stuff like that. But yeah, I
think we I don't know. That's just my
take on it. We probably want to keep the
>> keep it minimal. Yeah. And that's like
part of the point too, right? Like or
Yeah.
>> Well, it has to be maintained as a green
space. You can put parks. You can
there's, you know, you can put a bench.
I think there there's there there's a
specific list of what you can and cannot
place in terms of
>> cuz then there's like already that
little park on the corner and we don't
really do anything there, you know?
>> Right. Well,
>> what's that?
>> That's the state.
>> That's the state. I was telling that,
you know. No. Okay. So, I guess the
state doesn't do anything there,
>> right?
actually looked the best it has in a
while. I noticed a month or so ago,
maybe
>> back to over and
>> a lot of homeless people have been
hanging out there
>> or unhoused people or whatever, you
know, not whatever, but it's
>> been a and that's in fact one of the
reasons why Larry really said that he
that was the kind of the straw for him
is because he wasn't didn't feel safe
there.
So,
>> well, that's that's where it's all at.
>> Well, thank you very much for the
update. Yeah.
>> Everything else good?
>> Yeah.
>> All righty.
All right. Mike, did you have anything
else?
>> No. All right. I think I'm done with
that. Um, we have some documents reports
um in the approve
minutes, although I didn't get a chance
to approve or to read those. So, we'll
uh move that till next meeting.
Um,
and if there's nothing is there any
other new or old business?
So, why don't we go into executive
session? Hello.
>> Okay.
Um, is there something else?
>> No, I didn't know we were going I didn't
>> Yeah, there was a
>> I was just on there.
>> No, there was a request um from Sasha to
go into executive session for
confidential employee
um
discussion.
I would go ahead and move to do that.
Is there a second?
>> Second.
>> Sam. Thank you. All in all in favor I
>> I unless there's any other discussion.
>> Do I pause the recording then?
>> Yeah. Yeah. You want to shut right off?
>> Okay. You going to stop it?
>> Yeah, you stop cuz we'll uh come out and
we will
>> recording stop. Not until there will be
no business or no action taken.