Information session on the Plumbing Code of Australia 2025
Watch on YouTubeVideo summary
The presentation introduces the key updates to the Plumbing Code of Australia 2025, led by representatives from the Australian Building Codes Board, with a focus on enhancing safety, reliability, and practical application for practitioners. The session outlines that these changes are organized into four main areas: governing requirements in Section A, water services in Section B, sanitary plumbing and drainage in Section C, and updated reference documents. A central theme of the update is the clarification of compliance pathways, distinguishing between standard deemed-to-satisfy provisions and performance solutions that allow for alternative methods when specific conditions are met. This structural improvement aims to reduce ambiguity, ensuring that designs are robust and that evidence of suitability is clearly documented throughout a project's lifecycle.
Significant practical changes have been introduced regarding water services, particularly the separation of access and isolation requirements into distinct outcomes within Sections B1 through B7. For cold water systems, a new verification method known as B1V1 is available to assess velocity based on probable simultaneous design flow rather than conservative assumptions, potentially allowing for more efficient pipe sizing while maintaining hydraulic performance. Similarly, heated water and non-drinking water sections have been clarified to address issues like noise, erosion, and system longevity, while firefighting provisions now explicitly separate storage, access, and isolation requirements. Crucially, the code reinforces that plastic pipes must not be used above ground in combined sprinkler and hydrant systems, requiring careful coordination between plumbing specifications and fire safety designs to ensure material suitability and correct installation locations.
The updates also refine cross-connection control and sanitary drainage verification to better manage contamination risks and system capacity. In cross-connection control, hazard scenarios previously found in a separate specification have been relocated to Part B5, with clearer guidance on assessing individual and zone hazards using a three-step process that prioritizes determining the hazard before selecting backflow protection. For sanitary systems, the verification framework has been simplified into two linked methods: one to determine wastewater load and another to verify the system's capacity and arrangement. This distinction ensures that changes in fixture loads or drain gradients are properly accounted for, preventing performance issues caused by unverified assumptions about pipe diameter, grade, or junction types. Furthermore, the code now explicitly treats contamination prevention as a distinct performance requirement within sanitary drainage design.
Finally, the presentation emphasizes the importance of using the correct reference document editions and maintaining rigorous records of evidence of suitability. The 2025 edition of the AS/NZS 3500 series is adopted by default, but practitioners must be aware that newly published editions cannot be used unless listed in the new alternative reference documents register. This ensures consistency across projects and prevents the mixing of provisions from different editions unless a performance solution demonstrates their compatibility. Overall, while the Plumbing Code of Australia 2025 is designed to be more navigable, it demands careful attention to design coordination, product substitution checks, installation verification, and commissioning processes to ensure that plumbing systems remain safe, accessible for maintenance, and compliant with all relevant national and jurisdictional requirements.
Read the full video transcript
All right. Good morning, everyone. It's
now clicked over to 11. Um welcome to
today's presentation on the key changes
to the Plumbing Code of Australia
2025. My name is Adrian Piani.
I'm CEO of the Australian Building Codes
Board. And I appreciate you taking the
time to join us today.
Many of you will know the Plumbing Code
of Australia or PCA
as Volume 3 of the National Construction
Code
commonly known as the NCC.
The PCA sets the national technical
requirements for plumbing and drainage
systems in and around buildings.
As practitioners
regulators and industry representatives
your work
plays an essential role in ensuring
these systems are safe
reliable
and fit for purpose.
Today's session is designed to help you
understand the most significant updates
and what they mean in practice.
So, before we begin
I would like to acknowledge the
traditional custodians of the land
where I am here in Canberra
the Ngunnawal people
and acknowledge the traditional
custodians of the lands from which you
are all joining today.
I pay my respects to elders past and
present
and recognize their continuing
connection to country, culture and
community.
I also extend that respect to any
Aboriginal and Torres Strait Islander
peoples joining us today.
The presentation will focus on three
questions.
What has changed?
Why do these changes matter?
And what do practitioners need to do
differently?
We'll cover updates relating to water
services
cross-connection control,
rainwater,
sanitary plumbing and drainage,
reference standards, and evidence of
suitability.
While today's presentation provides a
high-level overview of the changes, we
encourage you to explore the detailed
amendment list and supporting resources
available
on the ABCB website.
So, before we get started, just a few
housekeeping items.
Your camera and microphone are off.
A short Q&A session will be held at the
end of the presentation. You can submit
questions at any time.
Please submit questions using the Q&A
function.
We'll do our best to answer as many
questions as we can.
If we don't get to yours, please check
our website resource library. It may
already be covered there.
The session will run for approximately 1
hour.
Today's session is being recorded and
will be made available on the ABCB
YouTube channel.
We will notify stakeholders once the
recording is available.
Please note that the Q&A session will
not be included in the recording.
With that,
I'll hand over to Richard Plain to take
you through the key changes. Thank you,
and I hope you find today's session
valuable.
>> Thanks, Adrian. My name is Richard
Plain, and I'm the plumbing director of
the ABCB.
Thank you for taking the time to be here
today.
This presentation is designed to provide
a practical overview of most significant
PCA 2025 changes.
Whether you work with the PCA every day,
or you need to refer to it occasionally,
I'll explain the main changes,
identify the relevant provision
references, and describe each change
means in practice.
Let's start off by looking at the major
changes to the PCA by section.
This slide groups the changes into four
areas.
First area is section A, which contains
the NCC governing requirements.
These rules explain how compliance is
demonstrated, how reference documents
are used, and what evidence may be
accepted.
The second area is
section B, which deals with water
services. This includes cold water,
heated water, non-drinking water, fire
fighting water,
cross-connection control, and rainwater
systems.
The third area is section C,
which deals with sanitary plumbing and
drainage. The main changes are revised
verification methods for determining
wastewater flow and verifying system
design.
The fourth area is reference documents
and guidance.
PCA 2025 adopts updated editions
of the AS/NZS 3500 series and introduces
a control process
when using an approved alternative
edition.
A useful starting point is
volume three list of amendments. It
identifies the changed provisions and
helps practitioners decide which changes
are relevant to a particular project.
Section A,
governing requirements.
Before looking at the plumbing
provisions, it is helpful to understand
section A.
Section A contains rules that apply
across the NCC, including volume three.
A2G2 explains the assessment methods
that may be used for a performance
solution. A performance solution is an
alternative way of meeting a performance
requirement when the proposed solution
does not follow the complete deemed to
satisfy pathway.
A4G1
deals with reference documents.
PCA 2025 introduces the alternative
reference documents register as an
option to schedule two.
An alternative edition can only be used
through this pathway when it's included
in the register.
For a deemed to satisfy solution or an
NCC verification method, one edition
must be used consistently.
Provisions from different editions
cannot be mixed unless the resulting
approach is demonstrated through a
performance solution.
A5G6
concerns evidence of the fire hazard
properties and combustibility.
This may be relevant when a plumbing
products, service penetrations, or
associated construction interact with
fire safety requirements.
For a practitioner who's new to the PCA,
practical message is simple.
First,
identify the suitable requirement,
then identify the compliance pathway.
Finally, make sure the evidence supports
the exact product design and intended
use.
Section B, water services,
contains the requirements for water
services.
Parts B1 to B7 cover different service
types, but PCA 2025
gives these parts a more consistent
structure.
Across the relevant parts, access and
isolation are now expressed as separate
outcomes.
Access means being able to reach a
component for inspection,
testing, maintenance, or replacement.
Isolation means being able to shut off
the relevant service section or
component.
These concepts are related, but they are
not the same.
An isolating valve may be in the correct
hydraulic position,
but still be difficult to reach.
A valve may also be easy to reach, but
shut off a larger area than intended,
such as a whole floor instead of one
tenancy.
The change supports better design
review,
installation, commissioning, and
maintenance.
Part B1 covers cold water services.
There are three main points on this
slide. First,
B1P2 is the performance requirement for
water velocity.
PCA 2025 introduces V1V1, a new
verification method for determining
whether a proposed cold water service
satisfies that velocity requirement.
A verification method is an assessment
method.
It gives a recognized way to test
whether a performance requirement has
been met.
Using B1V1 forms part of a performance
solution pathway. It is not the same as
following the deemed to satisfy
provision provisions in AS/NZS 3500 part
one.
Second, access and isolation are
separated.
B1P3 deals with access, and B1P4 deals
with isolation.
The design should therefore show both
where serviceable components are
located, and how the required parts of
the system can be shut off.
Third, B1D3 2 clarifies that plastic
pipes and fittings must not be used
above ground in a combined sprinkler and
hydrant system.
This resolves uncertainty created by the
different material rules that may apply
under the sprinkler and hydrant
standards.
For plumbers and reviewers, the
practical effect is that hydraulic
performance, access, isolation, and
material suitability must each be
considered.
Satisfying one of these outcomes does
not automatically satisfy the others.
Let's look at B1/V1 in more detail,
including how the method works and the
potential benefits it may provide.
B1/V1 is an optional verification method
for determining whether a proposed cold
water service
satisfies the velocity requirement in
B1/P2.
It does not replace the deemed to
satisfy provisions in AS/NZS 3500 Part
1.
Where B1/V1 is used, it forms part of a
full solution pathway.
The method starts by determining a
probable simultaneous design flow.
It uses a probability-based approach
that considers how fixtures are expected
to be used rather than assuming that
every connected fixture operates at the
same time.
The resulting high design flow is
commonly described as the Q99 flow.
In practical terms, Q99 represents a
high probable flow
for the assessed
fixture population and use pattern.
It provides a design flow input for
assessing velocity in each relevant pipe
section. The next step is to assess
velocity using the actual internal
diameter of the proposed pipe.
This is important because two pipe
products with the same nominal size can
have different internal diameters.
The selected product and its actual
internal bore must therefore be
consistent with the calculation.
One
One potential benefit of B1/V1
is that the cold water pipe work can be
assessed using a more project-specific
design flow.
Where supported by the calculation, this
may allow pipe work to be matched more
closely to the probable demand rather
than being based on a more conservative
assumption about simultaneous fixture
use.
This may support more efficient use of
pipe materials and associated
installation components.
However, any reduction in pipe diameter,
materials, or installation inputs
is potentially a project outcome, not an
automatic benefit of using B1/V1.
Another benefit is that B1/V1 provides
transparent and reproducible design
basis.
Consistent, the assessment should
identify the connected fixtures,
adopted probabilities, flow rates, pipe
sections, and actual internal diameters
used to obtain the results.
A reviewer should be able to examine the
scope, assumptions, and inputs, and
reproduce the controlling results.
It is important to understand that scope
of the method
B1/V1 addresses the B1/P2 velocity
requirement only.
It does not verify every aspect of the
cold water service.
The complete hydraulic design must still
consider the available supply pressure,
elevation, friction loss through pipes
and fittings,
fixture flow and pressure requirements,
noise, water hammer, and pipe
limitations.
For example, a branch servicing an upper
floor level shower may satisfy B1/V1
velocity requirement, but still have
excess pressure loss.
In that situation,
the pipe may need to be larger,
the design may need to change, or
another design response may be required.
Product substitution must also be
checked.
A replacement pipe may be the same
nominal size as the specified pipe, but
a different internal diameter.
This may change the calculated velocity
and pressure loss, meaning the original
assessment may no longer apply.
The installed system must therefore
remain consistent with the product's
dimensions, fixture population, and your
assumptions used in the assessment.
Where a change affects those
assumptions, the relevant part of the
design should be reviewed before the
change work proceeds.
The practical benefit of B1 V1 is not
simply small pipework. It is more
accurate and evidence-based method for
assessing cold water velocity that may
support design optimization where the
complete hydraulic assessment
demonstrates satisfactory performance.
The key message is that B1 V1 may allow
cold water pipework to be better matched
to probable demand, but it does not
automatically justify the smallest pipe.
The complete cold water service must
still perform as intended.
B2 heated water and B3 non-drinking
water.
This slide covers two parts with a
similar drafting approach.
Part B2 covers heated water services.
B2 P3 has been clarified including the
treatment of flow velocity in non-copper
circulatory systems.
This matters because excessive velocity
in a heated water circulation system can
contribute to noise, erosion, and
reduced system life.
B2
P4 now deals with access and P2 B5
deals with isolation. P2 D2 also updates
the minimum small scale technology
certificate values and provides a
limited option to use relevant volume
two provisions in specified
circumstances.
Part B3 covers non-drinking water
services.
The force requirements are now arranged
more clearly, including separate
requirements for access, isolation,
pressure, uncontrolled discharge, and
water efficiency.
For someone unfamiliar with the PCA, a
non-drinking water service may include
water used for toilet flushing,
irrigation, or another approved purpose.
The service must be clearly identified
and protected against cross-connection
with the drinking water service.
The common practical message is that
each service must perform hydraulically,
remain identifiable, be accessible for
maintenance, and be capable of
appropriate isolation.
Part B4 covers firefighting
services, including hydrant systems.
PCA 2025 separates the key performance
requirements.
B4P2 addresses access, B4P3
addresses isolation,
B4P4
addresses firefighting water storage,
and B4P5
addresses uncontrolled discharge.
B4D4
recognizes a fire hydrant system
installed in accordance with AS 2419
part one, AS 2118
part six where suitable, or FPAA
101H where applicable.
This provision identifies the applicable
systems pathways rather than creating a
material restriction.
The material restriction is addressed in
B1D3.
Plastic pipes and fittings must not be
used above ground in a combined
sprinkler and hydrant system.
So, the plumbing specification and fire
design need to be considered together.
The change also has cross volume
connection because volume one recognizes
combined sprinkler and hydrant systems
in the relevant fire safety provisions.
For practitioners, the action is to
confirm the system type,
the relevant standard,
the location of the pipework,
and the material limitations before
products are ordered or installed.
Part B5, cross connection control,
protects water services from
contamination caused by cross
connections.
A cross connection is an actual or
potential connection through which
contaminated water
or another substance can enter a water
service.
Backflow may occur through back
siphonage when upstream pressure falls
or back pressure
when downstream pressure becomes greater
than supply pressure.
In PCA 2022,
the detailed hazard scenarios were in
specification 41.
In PCA 2025,
specification 41 was deleted and the
contents of specification 41 relocated
to B5 D7 within part B5.
This is mainly a structural and
usability improvement. The hazard
scenarios now sit beside the provisions
that use the hazard ratings.
Most familiar low, medium, and high
hazard examples remain. Although some
descriptions have been clarified.
One example
is the wording for handheld personal
washing hoses.
PCA 2022 referred to handheld bidet
hoses and trigger sprays.
PCA 2025 now refers to handheld bidet or
douche hoses and trigger sprays.
The addition of the douche hoses makes
the listed scenarios easy to recognize
where the terminal that terminology is
used for the product or installation.
This is primarily a clarification of the
existing hazard description rather than
the creation of a new hazard category.
Consider a handheld bidet or douche hose
installed beside a toilet.
The assessment should be based on the
complete installed arrangement,
not only the product name.
A key practical consideration is whether
the hose outlet can reach into the
toilet pan and create an actual or
potential cross connection.
This is an example of a recognizable
hazard addressed by B5 D7 listed
scenarios.
Other cross connections may require
further assessment because not every
possible individual or zone hazard
is included in the list.
B5 D7 and B5 V1 assessment sequences.
The handheld bidet or douche hose is an
example of a hazard addressed by a
listed B5 D7 scenario.
However, not
individual or zone hazards will be
adequately covered by the B5 D7 list.
The following three-step process
explains how to deal with listed and
unlisted hazards.
Step one
is to compare the connection with the
scenarios identified in B5 D7.
Practitioners should consider the actual
operational circumstances of the
connection,
including its intended use and potential
contaminants, rather than relying solely
on the product name or classification.
Where a scenario in B5D7 is relevant,
the corresponding prescribed hazard
rating shall be assigned.
Step two applies when no B5D7 scenario
adequately covers the individual or zone
hazard.
B5V1
can then be used to determine the hazard
rating through a performance solution
pathway.
For a chemical hazard, the assessment
considers the substance that could enter
the water service,
its likely concentration,
possible chemical mixtures,
the connection arrangement, and the
consequences of exposure.
A safety data sheet is useful in
evidence,
but it does not determine the PCA rating
by itself.
Step three is to select suitable
backflow protection. The backflow device
must suit the determined hazard rating
and the possible backflow mechanism.
The design must also consider
orientation, pressure, drainage, access,
testing, and maintenance.
B5V1
cannot be used to lower a rating already
described by B5D7.
It also deals with individual and zone
hazards,
not the separate contaminant
requirements imposed by network utility
operator.
The key point is to determine the hazard
first and select the device second.
B6 and B7 rainwater.
PCA 2025
makes rainwater systems easier to
understand by separating the service
side from the storage side.
Part B6 covers the rainwater service.
In simple terms, this is the downstream
pipework that carries rainwater from the
storage connection to the points where
the water is used.
Part B7 covers rainwater storage. This
includes the tank, the entry of
rainwater, overflow arrangements, and
the connection from storage to
downstream services.
Both parts include clear requirements
for access and isolation. The broader
framework also deals with matters such
as contamination protection, pressure,
velocity, identification, and water
efficiency where relevant.
For example, a building may use tank
water for toilet flushing, laundry, or
irrigation.
A reviewer should be able to identify
the tank side obligations, the service
side obligations, and the point where
the two systems connect.
Each Any connection to a drinking water
supply must use the permitted
arrangement and include appropriate
cross-connection protection. The
rainwater pipework must always be
suitably identified so that it is not
mistaken for drinking water.
Access and isolation across section B
brings the reoccurring access and
isolation change together.
For access, ask whether a person can
reach the valve, pump, backflow device,
water heater, filter, or tank component
for the work it will need during its
service life.
For isolation, ask whether the correct
part of the service can be shut off. The
answer should be based on the intended
operation and maintenance arrangement,
not simply on whether any valve exists.
These matters should be checked during
design coordination. A valve shown in an
accessible position on a hydraulic
drawing may become blocked by a ceiling,
covered duct, or another service.
The check should be repeated during
installation and at completion.
Access that exists before fit out may be
lost after finishes and joinery are
installed.
The aim is a plumbing system that
remains practical to test,
maintain, and replace without causing
unnecessary disruption to unrelated
parts of the building.
Section C covers sanitary plumbing and
sanitary drainage.
Sanitary plumbing generally refers to
pipework within the building that
receives discharge from fixtures and
conveys it to the sanitary drainage
system.
Sanitary drainage generally refers to
the graded
drainage system that conveys the
wastewater towards the point of
connection.
The main PCA 2025 change is a clearer
verification framework.
The process separates the wastewater
load from the capacity
and arrangement of the proposed system.
In simple terms, the first question is
how much wastewater must the system
carry?
The second question is can the proposed
pipes, grades, junctions, and the other
components carry that flow safely?
C1 sanitary plumbing verification.
In PCA 2022, sanitary plumbing
verification was spread across C1 V2, C1
V1 to C1 V5.
PCA 2025 simplifies the pathway into two
linked methods.
C1 V1
determines the sanitary plumbing
wastewater flow rate.
It establishes the hydraulic load
produced by the connected fixtures
and expected pattern of use.
C1 V2 uses that flow rate to verify the
sanitary plumbing design.
It considers the proposed branches,
stacks, and other relevant parts of the
system.
The revised methods may support more
efficient pipe sizing where the
calculation justifies it.
They do not create a general permission
to reduce pipe diameters.
Pipe size is only one part of the
design.
Junction type, branch location, stack
offsets, ventilation, and the
relationship between connected fixtures
can also affect performance.
For example, a calculated design may be
based on a particular apartment stack
arrangement.
Moving a bathroom group, adding a
commercial fixture, or changing a branch
connection may alter the assumptions and
require the design to be reviewed.
The practical message is that C1 V1
determines the load and C1 V2 verifies
the sanitary plumbing capacity and
arrangement.
The installed system must match the
assessed design.
C2 sanitary drain verification.
Part C2 applies the same general load
and capacity logic to sanitary drainage.
C2 V3 determines the sanitary drain
wastewater flow rate.
PCA 2025 revises this method.
C2 V4 is a new verification method for
sanitary drain design. It uses the
calculated flow to assess matters such
as pipe diameter,
grade, junctions, invert levels, and
downstream conditions.
This distinction is important on site.
Adding fixtures may change the C2 V3
flow rate.
Changing the drain grade may leave the
fixture load unchanged, but alter the C2
V4 result.
For example,
rock or another service may force a
drain to be installed at a flatter grade
than shown on the design.
Keeping the same pipe diameter does not
automatically preserve the verified
performance.
C2 P5 also makes contamination more
visible as a distinct performance
requirement.
The design must prevent the sanitary
drainage system from creating
unacceptable contamination risk.
The practical message is that C2 V3
determines the load,
while C2 V4 verifies the capacity
and arrangement of the drain.
Related plumbing changes outside volume
three.
Some changes outside volume three
directly affect plumbing work and
coordination.
The swimming pool drainage, volume one
G1D5,
and volume two H2D2 provide a deemed to
satisfy pathway for pumped swimming pool
discharge to sanitary drainage in
accordance with AS/NZS 3500 part two.
Network operator requirements still need
to be checked.
Volume one also recognizes combined
sprinkler and hydrant systems in
relevant fire safety provisions.
This reinforces the core This references
the need to coordinate the fire design
with the material restriction explained
on slide 10.
Changes concerning roof, balcony, and
podium drainage may affect outlet and
location overflow arrangements, falls in
coordination with structural substrates.
The PCA should therefore not be read in
isolation. A plumbing system may also be
affected by volumes one or two,
reference standards, jurisdictional
legislation, and authority requirements.
Reference documents.
The NCC sets the required outcomes and
relies on reference documents for much
of the detailed design and installation
information.
Schedule two identifies the editions
adopted by the PCA 2025,
including the 2025 editions of AS/NZS
3500 plumbing and drainage series.
The latest edition available for
purchase is not automatically the
edition adopted by the NCC.
For every project, record the applicable
NCC edition, jurisdiction, and reference
document editions.
A4G1 introduces the alternative
reference documents register.
The register provides a controlled way
to use an approved alternative edition
of a reference document before the next
full edition of the NCC.
A newly published edition
cannot be used through this pathway
unless it has been assessed and listed.
Each register entry identifies where the
alternative edition may be used and may
include conditions, exclusions,
or directions about secondary reference
documents.
Where an entry applies, a project may
use either the schedule two edition or
the listed alternative edition for the
provisions [clears throat] covered by
that entry.
For a deemed to satisfy solution
or an NCC verification method, use one
edition consistently. Do not combine
provisions from different editions.
A mixed edition approach must be
demonstrated through a performance
solution.
Record the selected edition and
applicable register entry in the project
documentation.
The register does not apply to state or
territory variations unless the entry
states otherwise.
Evidence of suitability
is the information used to show that
material, product, design, or form of
construction is suitable for its
intended use under the NCC.
The ABCB evidence of suitability
handbook provides a decision framework.
It prompts users to check whether the
evidence type is recognized by the NCC,
current and relevant to the proposed
application.
Relevance is critical. A certificate or
report may cover a product family, but
not the exact model,
size, material, configuration, or
installation proposed.
Where a WaterMark certification is
required, a WaterMark license is
important evidence. However, it does not
automatically establish every aspect of
the PCA compliance.
Check the certified specification,
authorized scope of use,
conditions, and installation
limitations.
Apply the same approach to test reports,
calculations, certificates,
expert evidence, and assessment methods.
Read the complete evidence, not only the
title or conclusion.
The handbook is guidance. It supports
consistent assessment but does not
approve a product or create a new
evidence type.
Practitioner checklist.
This checklist turns the changes into
project actions.
At design stage, identify the NCC
edition,
jurisdictional variations, and
applicable performance requirements.
Confirm whether the solution is deemed
to satisfy or includes a performance
solution.
Before purchasing or substituting a
product, check the applicable
filing standard, watermark requirements,
evidence scope, and intended use.
A substitution is a design and
compliance decision, not only a
purchasing decision.
During installation, confirm that
materials, internal diameters, grades,
fittings, and layouts match the approved
design.
Keep required components accessible and
ensure isolation operates as intended.
If a change affects a verification
method or hydraulic calculation,
have it reviewed before proceeding.
At completion, test and commission the
system, record the standard editions
used, and retain calculations,
certificates,
test results, conditions, and
limitations.
ABCB educational material.
Before we wrap it up, I'd like to
highlight some resources that can help
you apply PCA 2025 in practice.
After today's session, a good starting
point is Volume Three list of
amendments.
It can help you quickly identify which
changes are relevant to your projects
and where those changes are located in
the code.
Once you identify the relevant
provisions,
make sure you confirm applicable
reference document editions. Schedule
two remains the starting point,
and where relevant, the alternative
reference documents register can help
you determine whether an approved
alternative edition is available.
If your project involves a you a
verification method, a performance
solution, or a product evidence,
resources such as the performance
solution process handbook and the
evidence of suitability handbook can
help provide useful practical guidance.
Finally,
if you're looking to build your
knowledge further,
NCC tutor,
CPD resources, and the plumbing and
drainage resource library provide
additional learning opportunities
that you can assess at any time.
As always, these resources are designed
for understanding and application of the
NCC. They do not replace the adopted NCC
reference standards, jurisdictional
requirements, or network utility
requirements.
PCA 2025 key takeaways.
For water services, the major points are
the new B1 V1 velocity method,
clearer access and isolation
requirements, and changes across parts
B2 to B7.
For cross connection control,
specification 41 has moved into B5 D7,
and B5 V1 remains the route for
determining
general unlisted individual and zone
hazards.
For sanitary systems, C1 V1 and C1 V2
provide a simpler sanitary plumbing
pathway, while revised C2 V3 and the new
C2 V4 makes entry drainage verification
more explicit.
For reference documents and evidence,
PCA 2025
adopts
the 2025 AS/NZS 3500 series,
introduces the alternative reference
documents register,
and reinforces the need to check every
scope and intended [clears throat] use.
Overall, PCA 2025 is easy to navigate,
but the changes still have practical
consequences for design,
product selection, installation,
commissioning, and record keeping.
I'd like to leave you with four key
messages from today's presentation.
First, access and isolation are now more
clearly expressed
throughout the water services
provisions, and should be considered
separately during design, installation,
and maintenance.
Second,
several new and revised verification
methods have been introduced.
These methods can support more
sophisticated design approaches,
but they must be applied correctly and
as part of a complete design process.
Third, when dealing
with cross connection control, determine
the hazard first,
and then select the appropriate backflow
protection.
Finally,
always ensure you're working with the
correct reference document edition,
schedule two, and where applicable, the
alternative reference documents register
should be at your starting point.
Overall, PCA 2025 is easier to navigate,
but it still requires careful
consideration of design,
product selection, installation,
commissioning, and record keeping.
And I will now hand back to Adrian to
kick off
Q&A session.
Thank you.
>> Thank you, Richard, for the
presentation.
We've covered the main changes to water
services,
cross connection control,
rainwater, sanitary plumbing and
drainage, reference documents, and
evidence of suitability.
As always, the best starting point for
any project is the adopted PCA,
followed by the relevant reference
standard,
jurisdictional variations, and authority
requirements.
So, we'll now go through the questions,
and remember to pop them in the chat.